NCAT Confirms Expired Section 106(5) Damages Claims Are Not Revived Under New Six Year Limitation Period

NSW

Changing limitation periods in NSW strata legislation have created confusion, with many mistakenly assuming that the new six year time frames automatically revive expired claims. This misunderstanding can place pressure on owners corporations, who may face unexpected demands for compensation long after they believed their exposure had ended.

Tribunal Confirms Expired Claims Cannot be Revived Under Extended Limitation Period

Grace Lawyers recently secured an important outcome for an owners corporation, with the Tribunal dismissing a lot owner’s damages claim under Section 106(5) of the Strata Schemes Management Act 2015 (NSW) on the basis that it was commenced outside the original two‑year limitation period—even though the legislation now provides a six‑year period. The lot owner had become aware of the loss of rent in 2021 but failed to commence proceedings within the two‑year timeframe then required under Section 106(6).

Owner Argues Daily Loss Revives Claim Despite Original Limitation Period Expiration

On 1 July 2025, the amendment extending the limitation period under Section 106(6) of the Strata Schemes Management Act 2015 (NSW) from two years to six years came into effect. Relying on this change, the lot owner commenced NCAT proceedings seeking loss‑of‑rent damages under Section 106(5), despite acknowledging that he had previously allowed the original two‑year period to lapse. He argued that the legislative amendment revived his claim and, alternatively, that he could still recover damages accruing after 1 July 2025 on the basis that a fresh loss arose each day the common property remained in disrepair.

NCAT Confirms no Retrospective Operation of New Limitation Period

Acting for the owners corporation, Grace Lawyers sought summary dismissal of the damages claim on the basis that once the original two‑year limitation period had expired, the later extension to six years did not revive it. We argued that there is a strong presumption against legislation operating retrospectively, and that a proper reading of the amending provisions showed Parliament did not intend the new six‑year period to apply to claims already out of time. The Tribunal accepted these submissions and dismissed the lot owner’s loss‑of‑rent claim in full.

NCAT Ruling Eases Administrative and Financial Burdens for Owners Corporations

This decision, if applied consistently by the Tribunal, offers significant relief to owners corporations already grappling with the growing complexity of recent strata law reforms. These reforms have increased administrative obligations while simultaneously making financial management and levy recovery more challenging. By confirming that previously expired claims are not revived under the new six‑year limitation period, the decision reduces the volume of historical claims owners corporations must address—particularly those they had reasonably treated as final.

 

Summary

The evolving time limits in NSW strata legislation are making it harder for lot owners to understand their legal position. A recent NCAT decision has clarified that extending the limitation period for Section 106 damages claims from two years to six does not revive claims that had already expired. In this case, a lot owner attempted to rely on the legislative change to pursue a loss‑of‑rent claim long after the original timeframe had lapsed. The Tribunal rejected that approach, confirming that the amendment does not operate retrospectively and that expired rights cannot be reopened under the new regime.

 

Written by Peter Ton, Partner, Grace Lawyers, NSW

 

If you require guidance on how the changing limitation periods affect your claim or liability, speak with our NSW strata law team today on 1300 144 436.

 

When Words Cause Damage: Defamation in Strata Communities – Part 1

QLD

In strata communities, information moves quickly and disputes can escalate just as fast. When comments cross the line from criticism to defamation, the legal consequences can be significant. Defamation within strata schemes is becoming increasingly common, yet many owners and committee members misunderstand how the law applies. This article explains the essentials of defamation, the unique protections and risks in strata settings and the practical steps needed to avoid costly and unnecessary legal conflict.

What is defamation?

Defamation law developed to protect reputations. It is contained in uniform laws throughout Australia, with Queensland adopting the Defamation Act 2005, and in law made by the Courts (called common law).

A person making a defamation claim must prove that material:

  1. was published (ie communicated to a third party orally or in writing);
  2. reasonably identifies them (ie by name, by position);
  3. carries defamatory meanings (ie meanings that lower estimation, or cause others to shun or avoid);
  4. causes (or is likely to cause) serious harm/serious financial loss.

Only certain companies can sue for defamation, so it is important to obtain advice about whether your company is eligible. Alternative claims are available if a company is unable to sue under defamation law.

Defamation is not about hurt feelings. Criticism or insults are not necessarily defamatory.

How does defamation law apply to strata?

Defamation law applies in strata in much the same way as in other contexts. There are, however, added protections and considerations unique to strata.

Protections

Parliament introduced a vaccine into the Body Corporate and Community Management Act (Qld) 1997 to protect committee members from civil liability, including defamation. However, these protections are limited, and committee members must act cautiously to avoid exposure to potentially expensive legal action.

Section 101A gives committee members general protection from civil liability. This section does not extend to protect a committee member from criminal liability and is conditional on committee members acting in good faith and without negligence.

In St Minivers [2017] QBCCMCmr 352, Adjudicator Rosemann stated:

“…a liability claim against individual committee members would need to establish some element beyond a simple error or oversight. Considerations might include, for example, that the committee members were on notice that they were not entitled to approve the spending and acted despite that, that they knew the majority did not approve the scaffolding, that they personally benefited from the decision, that the conduct was objectively unreasonable in the circumstances, and/or that the Body Corporate or other owners suffered specific harm as a consequence of the decision.”

The person making the claim will bear the onus of proving the committee members acted negligently and in bad faith.

Section 111A gives committee members protection from liability for defamation. This protection is limited to when a committee publishes required material for a general meeting of the body corporate and that required material contains defamatory matter.

‘Required material’ is defined to include:

  1. a motion (including the substance of a motion) submitted other than by or for the committee for the general meeting;
  2. an explanatory note for such a motion that is prepared by the submitter of that motion.

Notably, the protection does not apply to:

  1. committee meeting material;
  2. general meeting motions submitted by the committee;
  3. all material that may be published by a committee, such as an explanatory schedule prepared by the committee and published with the general meeting material.

Section 24 of the Defamation Act (Qld) 2005 provides that a defence under that Act (including under the common law) is additional to any defence or exclusion of liability available to a person under other law. This means that, if defamatory material is published outside of the limited protections offered by section 111A of the body corporate legislation, there may still be a valid defence to a defamation claim.

Insurance

The insurance for a community titles scheme will generally contain a policy covering office bearer’s liability. However, this policy will generally contain an exclusion from protection for defamation. This means that if a defamation claim is made against a committee member, the insurer will generally not provide cover for any costs incurred defending that claim under its standard policy.

Costs

There are statutory restraints regarding how a body corporate may apply its funds. Paying for costs incurred by a committee member defending (or initiating) a defamation claim is not usually considered a cost that falls within the functions of a body corporate.

But, in The Glades-Peninsula [2019] QBCCMCmr 37, Adjudicator Rosemann stated:

“There could conceivably be circumstances where it might be reasonable for a body corporate to pay the legal costs of a committee member arising from actions or omissions taken by them in their capacity as a committee member on behalf of the body corporate. However, I am of the view that such circumstances would be limited. For example, if there was a legal claim relating to actions or omissions that were specifically authorised by the committee or were in accordance with specific statutory obligations, it might be appropriate for a body corporate to indemnify the committee member. However, the mere fact that a person was a committee member at the time that they made comments that another person objected to, or that comments were made in a body corporate meeting, would not be sufficient in my view.”

Republication

A person that publishes defamatory material will be liable for the repetition of the original publication if:

  1. he or she expressly or impliedly requested or authorised the repetition of the original publication;
  2. he or she intended that the repetition should take place;
  3. the repetition is the natural and probable consequence of the original publication; or
  4. there is a duty or obligation on the recipient of the original publication to repeat the original publication.

Common occurrences in strata include:

  1. at least 25% of owners in a scheme have signed a notice requisitioning an EGM that contains defamatory material, which is then required to be sent to all owners, recorded in minutes and put on body corporate records;
  2. a committee instructs a body corporate manager to distribute a document containing defamatory material to some (or all) owners.

Grapevine effect

This principle recognises that defamatory material is rarely confined to those to whom the matter is originally published. Where defamatory matter reaches a much wider audience than the original publication, it can impact the extent of damages awarded to a successful plaintiff. In strata, the grapevine effect is realised through a body corporate’s requirement to maintain records and interested persons being able to access those records (we will discuss more about withholding certain records in the next article).

Social media platforms

The High Court determined that a person who facilitates, encourages, and assists in the posting of comments by others can themselves be considered a publisher of the defamatory material and liable for defamation.

This means that any person that hosts a group social media page for your scheme can be liable if something defamatory is posted to the group or included in a comment to a post by someone else. Tight controls around approving posts and restricting comments to posts should be enacted, particularly with the transient nature of committee members.

What is the effect of an apology?

An apology for an alleged defamatory statement is not an admission of guilt. If a person (or someone acting on their behalf) apologises, that apology cannot be used to prove they were at fault or legally responsible. It also cannot be taken into account when deciding liability. This allows people to apologise or correct statements without automatically exposing themselves to legal consequences, and it can help resolve conflicts early before they escalate.

If a defamation claim goes to court, the defendant is allowed to rely on evidence that they apologised to the person who was defamed. While an apology does not mean the defendant admits fault, it can reduce the amount of damages the court may award.

When must a defamation proceeding be commenced?

A defamation proceeding must be commenced within one year from the date of the publication. Before proceedings are commenced, a concerns notice must be given to the potential defendants. The deadline for commencing proceedings can be extended by up to 56 days depending on the timing of the issuing of a concerns notice.

 

Written by Brendan Pitman, Partner, Grace Lawyers, QLD

 

If you are concerned about possible defamation in your Queensland body corporate community, early advice can make all the difference. Speak with our team on 1300 144 436 for practical, informed advice.

 

Why Owners Corporations Should Engage a Specialist Building and Construction Lawyer

NSW

Building and construction issues within strata schemes can be disruptive, costly and legally complex. Whether the matter involves building defects, incomplete works, contract disputes, or common property damage, lot owners face a legal landscape shaped by technical legislation, strict timeframes and specialised dispute‑resolution pathways. In this environment, the quality of legal advice is critical.

While many people instinctively turn to a local family or general practice lawyer, construction law is not an area where generalists can safely “dabble.” The risks are too high, and the consequences of incorrect advice can be significant. Engaging a specialist building and construction lawyer ensures that lot owners receive accurate, strategic and industry‑informed guidance from the outset.

This article explains why specialist expertise matters, outlines the key legislation governing building disputes, and highlights the essential points lot owners must understand when navigating construction issues.

The legislative framework governing building and strata disputes

Strata and construction matters in New South Wales are governed by a complex network of legislation, including:

  • Home Building Act 1989 (NSW) – Statutory warranties, licensing, and residential building work requirements.
  • Strata Schemes Management Act 2015 (NSW) – Responsibilities for common property, defect claims, and strata committee obligations.
  • Building and Construction Industry Security of Payment Act 1999 (NSW) – Payment claims and adjudication processes.
  • Civil and Administrative Tribunal Act 2013 (NSW) – NCAT’s jurisdiction and procedures.
  • Design and Building Practitioners Act 2020 (NSW) – Duty of care obligations and compliance declarations.
  • Environmental Planning and Assessment Act 1979 (NSW) – Development approvals and compliance.

A specialist construction lawyer works with these laws daily and understands how they interact in practice. A generalist lawyer may not have the depth of experience required to navigate this framework effectively.

Why lot owners need a specialist building and construction lawyer

  1. Accurate interpretation of construction contracts

    Construction contracts—whether for remedial works, upgrades, or new builds—contain detailed provisions relating to variations, delays, defects, payment schedules, and dispute‑resolution mechanisms. A specialist lawyer understands these clauses and ensures compliance with the Home Building Act and other legislation. This reduces the risk of disputes and protects lot owners from unfair contractual terms.

  2. Understanding of technical construction issues

    Building disputes often involve complex technical matters such as waterproofing failures, structural defects, fire safety non‑compliance, or incomplete works. A specialist lawyer is familiar with engineering reports, expert evidence, and industry standards. This allows them to quickly identify the core issues and develop a strategy grounded in both legal and technical realities.

    General practice lawyers may struggle to interpret technical evidence or understand the practical implications of construction‑specific issues.

  3. Effective dispute resolution that avoids costly court proceedings.

    One of the most significant advantages of engaging a specialist construction lawyer is their ability to resolve disputes efficiently and without unnecessary escalation. Court proceedings can be lengthy, expensive, and disruptive for lot owners. A specialist understands the dispute‑resolution pathways available under the Home Building Act, the Strata Schemes Management Act, and the Security of Payment Act, and uses this knowledge to guide clients toward early, cost‑effective outcomes.

    Through strategic negotiation, mediation, and targeted use of expert evidence, a specialist can often resolve issues long before litigation becomes necessary. This approach saves lot owners substantial time, stress, and financial burden.

  1. Experience with NCAT and specialist forums

    Many building disputes involving strata schemes are heard in the NSW Civil and Administrative Tribunal (NCAT). NCAT has unique procedural rules, strict evidence requirements, and specific expectations regarding expert reports and Scott Schedules.

    A specialist construction lawyer:

    • Appears regularly before NCAT
    • Understands how tribunal members approach building matters
    • Prepares compliant evidence and submissions
    • Ensures statutory warranty claims are properly framed
    • Manages expert evidence in accordance with tribunal rules

    This experience significantly improves the likelihood of a favourable outcome.

  2. Cost‑effective advice through efficiency

    Although a specialist may have a higher hourly rate, they typically resolve matters more efficiently because they already understand the issues, the legislation, and the dispute‑resolution pathways. This efficiency often results in lower overall legal costs and a more streamlined process.

  3. Proactive risk management for lot owners

    A specialist construction lawyer helps lot owners and strata committees:

    • Identify risks before signing contracts
    • Ensure compliance with statutory warranties
    • Recognise early signs of builder non‑compliance
    • Respond promptly to defective or incomplete work
    • Preserve rights under the Home Building Act and the Design and Building Practitioners Act

    Proactive advice can prevent disputes and protect the financial interests of the entire strata scheme.

Key points lot owners must understand about building and construction disputes

  1. Statutory warranty timeframes are strict

    Under the Home Building Act, lot owners must act within:

    • 6 years for major defects
    • 2 years for all other defects

    Delaying action can result in the loss of legal rights.

  2. Common property defects are the Owners Corporation’s responsibility

    Lot owners should understand:

    • The owners corporation must repair and maintain common property
    • Defect claims often involve both individual lots and common property
    • The strata committee must act promptly to avoid further damage or liability
  3. Expert evidence is critical

    NCAT and courts rely heavily on expert reports. A specialist lawyer ensures:

    • The right expert is engaged
    • Reports comply with tribunal rules
    • Evidence is strategically presented

    Poorly prepared expert evidence can undermine an otherwise strong claim.

  4. Early intervention prevents escalation

    The earlier a specialist lawyer becomes involved, the more options are available to resolve the matter efficiently. Early advice can prevent:

    • Builder disputes from escalating
    • Payment issues from becoming Security of Payment claims
    • Defects from worsening
    • Rights from expiring
  5. Not all lawyers understand strata construction law

    General practice lawyers may unintentionally:

    • Misinterpret construction contracts
    • Miss statutory deadlines
    • File incorrect applications
    • Provide incomplete or inaccurate advice

    These errors can significantly weaken an owners corporation’s position.

How Grace Lawyers can help

Grace Lawyers has a dedicated team of Building and Construction specialist lawyers who act exclusively for owners corporations. Daniel Radman, Managing Partner at Grace Lawyers, leads the firm’s building and construction practice. Daniel and his team have acted for Owners Corporations in numerous leading building cases including the only two strata defect matters decided in the High Court of Australia:

Summary

Construction and strata disputes are complex, technical and governed by strict legislative requirements. Engaging a specialist building and construction lawyer ensures that lot owners receive accurate, strategic, and efficient advice tailored to the unique challenges of building defects, contract disputes, and common property issues.

From contract review and risk management to dispute resolution and NCAT representation, a specialist lawyer provides the expertise necessary to protect your rights and achieve a cost‑effective, timely resolution. Given the financial and legal risks involved, choosing a specialist is not only prudent—it is essential.

 

Written by Daniel Radman, Managing Partner, Grace Lawyers

 

If you require guidance on a strata, building defects, or construction dispute, our specialist lawyers are ready to assist. Contact us now on 1300 144 436 for precise, informed advice that safeguards your project and your position.

When Breach Notices Fail: Legal Options for Owners Corporations Dealing with Problem Renters

VIC

When a renter repeatedly breaches owners corporation rules, the impact can extend far beyond minor inconvenience. Persistent anti-social behaviour, threats to resident safety, damage to common property and ongoing nuisance complaints can quickly disrupt an entire community.

While owners corporations have enforcement powers under the Owners Corporations Act 2006 (Vic), those powers are often limited when dealing with occupiers who simply ignore breach notices and continue their conduct. In these situations, understanding the responsibilities of the lot owner and the remedies available under other legislation becomes critical. This article explores the options available to owners corporations (OC) when a renter refuses to comply with the rules and practical steps that can be taken to resolve persistent breaches.

Who must comply with Owners Corporation rules?

Section 141 of the Owners Corporations Act 2006 (Vic) (OCA) provides that the rules of an OC are binding on the OC, lot owner, any lessee or sub-lessee of a lot and any occupier of the lot. Lot owners who do not live in their lots must give the occupier a copy of the OC rules under section 143 and occupiers of lots have a legal obligation to ensure their guests also comply with OC rules under section 141A.

What can an Owners Corporation do when rules are breached?

The OC’s powers under the OCA for an anti-social occupier is limited. Their powers are confined to issuing notices to rectify breaches under section 155 of the OCA and subsequently seeking orders from VCAT requiring the occupier to rectify the breach.

But what happens if the breaches are persistent, cannot be remedied, and the notices to rectify the breach are ignored and disregarded?

Practically, in those circumstances, paperwork will not resolve the persistent breaches and may agitate an anti-social occupier.

As the OC does not have the power to evict an occupier from a lot, it must consider alternative steps beyond the OCA.

When the lot owner must step in: Remedies under the Residential Tenancies Act

The Residential Tenancies Act 1997 (RTA) permits a rental provider (i.e. lot owner) to issue notices of breach to renters who cause a nuisance, interfere with the peace, comfort and privacy of neighbours and cause damage to the common property.

To escalate a notice of breach, a rental provider can issue a notice to vacate to renters who cause damage to common property, endanger others including neighbours or engage in serious threats and intimidation to the rental provider or its agent.

Importantly, the powers conferred by the RTA are exercisable by the rental provider, not the owners corporation. As a result, an OC’s ability to address problematic tenant behaviour will often depend on whether the lot owner is willing to take appropriate enforcement action.

If a lot owner fails to demonstrate that they are taking reasonable steps to address the breaches or recover possession of the property (in cases of serious misconduct), the OC may take action directly against the lot owner for failing to comply with their obligations under the tenancy agreement or their duties under the RTA.

In Leonard and Pekar v Tein and Cheng [2002] VCAT 729 (10 October 1998) VCAT stated that a neighbours’ reasonable peace, comfort and privacy is protected by the RTA and a landlord who does not safeguard those interests for other lot owners may be in breach of their obligations under section 60 of the RTA.  Notably, Member O’Dwyer stated:

  1. … The ultimate remedy against a recalcitrant tenant who continues to breach the duty provision is to obtain an order for possession.
  2. However, although the Act imposes a primary obligation on a tenant not to breach s60, by necessary inference it also imposes an obligation on a landlord to ensure that a landlord does all things necessary to stop any interference by a tenant with the reasonable peace comfort and privacy of occupiers of neighbouring premises. The landlord owes that obligation to occupiers of neighbouring premises and a wilful failure on the part of the landlord to satisfy that obligation entitles the neighbours to seek redress in this Tribunal against both the offending tenant and remiss landlord.

In that case VCAT referred also to section 472(1)(b) which provides that the Tribunal, on an application to or proceedings before it, may make any orders it thinks fit, including:

“(b) to require any action in the performance of a tenancy agreement or of duties under this Act relating to the tenancy agreement.”

VCAT added:

  1. That section empowers the Tribunal to require any action in the performance of duties under the Act. I propose that the landlord be forced to make an application for possession in order that the landlord perform her duty to the applicants.

Therefore, lot owners who do not occupy their lots should also be mindful that they must take reasonable steps to breach or evict an occupier who persistently causes a nuisance, damage to common property or interferes with the peace, comfort and privacy of neighbours.

Case Study: How an Owners Corporation addressed persistent tenant misconduct

A renter in a high-rise apartment was persistently causing a nuisance to their neighbours who shared the same floor. Their behaviour caused damage to apartment doors, requiring the OC to replace doors on a frequent basis. The renter also made his neighbours feel unsafe in the hallway which required the OC to engage 24/7 security staff specifically for that floor.

Following multiple breach notices served on the lot owner and the renter, it was clear that they were not effective and the renter continued to breach the OC rules.

The OC engaged Grace Lawyers to act for the OC and we recommended that on the lot owner (rental provider) make an urgent application to VCAT to take possession of the lot. Their VCAT application was successful with the support of affidavits from other lot owners detailing their safety concerns about the renter’s behaviour. The renter was evicted which required a warrant to be executed. We successfully claimed a portion of the OC’s security costs against the rental provider together with the costs to replace the apartment doors, due to those costs being incurred by the OC as a direct consequence of their renter’s behaviour.

Practical steps for Owners Corporations

When dealing with a renter who repeatedly breaches OC rules, the following measures can assist an owners corporation to effectively document, manage and escalate the issue:

  1. Remind lot owners of their obligations to ensure their occupiers and guests comply with the OC rules under sections 143 and 141A of the OCA.
  2. Keep a documented record of all breaches of OC rules committed by the occupier and issue notices to rectify to the occupier and copied to the lot owner.
  3. If the breaches escalate and cause damage to common property, endanger others or constitute threatening or intimidating behaviour, encourage the lot owner to issue a notice to vacate to the occupier and request evidence of the steps taken to evict the occupier.
  4. Failing the lot owner taking those steps, make an application to VCAT against the lot owner for breach of their duties.

Summary

While owners corporations have limited powers to directly address persistent misconduct by renters, they are not without remedies. Prompt enforcement of OC rules, thorough record keeping and early engagement with lot owners are critical to managing ongoing breaches. Where a renter’s behaviour escalates and the lot owner fails to act, VCAT may provide a pathway to compel action. A proactive and strategic approach can help restore amenity, protect residents and minimise the costs associated with ongoing misconduct.

 

If a renter’s behaviour is disrupting the peace, comfort or safety of residents within your scheme, our Victorian team can assist you to understand your rights and enforcement options. Contact us on 1300 144 436 for advice.

 

Written by Leila Idris, Partner, and Katrina Lay, Associate, Grace Lawyers

 

 

Last updated on 27 October 2026

Victorian Supreme Court Redefines Balcony Repair Responsibility in Damjanovski Decision

VIC

This article summarises the recent Supreme Court of Victoria decision in Damjanovski v Owners Corporation 1 Plan No. PS503570D [2026] VSC 656.

The decision is one of the most significant Victorian decisions in recent years and has far-reaching consequences for Owners Corporations, strata managers and lot owners.

The briefing will examine the factual background to the dispute, the Supreme Court’s interpretation of the relevant plan of subdivision, the Court’s consideration of the meaning of “interior face”, and the implications of the decision for determining whether balcony waterproofing systems form part of common property or private lot property.

How did the balcony repair dispute arise?

The proceeding concerned a long-running dispute regarding water ingress originating from a fifth-floor balcony within a residential apartment development in Maribyrnong.

Mr Damjanovski purchased the apartment off the plan in 2002. From approximately 2007 water ingress was reported in apartments beneath Mr Damjanovski’s apartment. Expert investigations ultimately determined that water was entering lower lots due to several defects, including but not limited to:

  • the tiled balcony surface;
  • the waterproofing membrane; and
  • the screed beneath the tiles.

The Owners Corporation contended that the balcony floor, including the tiles, waterproof membrane and screed, formed part of Mr Damjanovski’s lot and that he was therefore responsible for repairing and maintaining those components.

Accordingly, Notices to Repair were issued in November 2022 and March 2023 requiring Mr Damjanovski to undertake remediation works to the balcony.

Mr Damjanovski commenced proceedings in VCAT seeking declarations that the Notices to Repair were invalid and that responsibility for the defects rested with the Owners Corporation.

At first instance, VCAT accepted the Owners Corporations’ position and concluded that the boundary of the lot was located at the surface of the structural concrete slab. On that basis, VCAT determined that the tiles, screed and waterproof membrane situated above the slab formed part of Mr Damjanovski’s lot.

Mr Damjanovski appealed the decision to the Supreme Court of Victoria.

What laws govern balcony repair responsibility?

The principal legislative provisions considered by the Supreme Court were:

  • sections 4, 46 and 47 of the OCA;
  • sections 48 and 49 of the OCA;
  • section 129 of the OCA;
  • section 12 of the Subdivision Act 1988 (Vic) (SA);
  • the relevant plan of subdivision; and
  • the Subdivision (Procedures) Regulations 2000.

The dispute ultimately centred on the proper interpretation of the plan of subdivision and, the meaning of the notation that boundaries defined by buildings were located at the “interior face” of the building.

What was the Supreme Court decision?

Ultimately, the Supreme Court overturned VCAT’s interpretation of the plan of subdivision.  Specifically, the central issue was whether the expression “interior face” referred to:

  • the surface of the structural concrete slab; or
  • the visible surface of the completed balcony floor.

VCAT adopted the former approach, finding that the structural slab represented the relevant boundary and that everything above it formed part of the lot. Harris J rejected that interpretation.

Her Honour observed that the relevant question was where the boundary lies when a balcony floor consists of multiple building layers, including:

  • a structural concrete slab;
  • screed;
  • waterproof membrane; and

The Court held that “interior face” referred to the interior face of the building itself, being the visible face of the completed building rather than the structural slab lying beneath the finished surface. Harris J stated:

“the better view is that the effect of the Plan of Subdivision is that the concrete slab floor of the Balcony, and the slab, membrane and tiles affixed to it, is common property.”

The Court further held that “the surface of the tiles is the interior face” and concluded that the tiles, waterproof membrane and screed should all be considered common property.

Accordingly, the Court held that:

  • the tiles were common property;
  • the waterproof membrane was common property; and
  • the screed was common property.

Because those building elements were determined to be common property, the Court determined that VCAT had erred in declaring that Mr Damjanovski breached section 129 of the OCA by failing to repair and maintain his lot.

The Court further held that the Notices to Repair could not properly be supported by section 48 of the OCA because that section only applies where repairs are required for a lot owner’s lot.

Why is the Damjanovski decision so important?

This decision is likely to become the leading Victorian authority on the interpretation of interior faces in plans of subdivision prior to 2011.

Perhaps most significantly, the decision substantially undermines the approach previously adopted in Owners Corporation PS508732B v Fisher [2014] VCAT 1358.

In Fisher, VCAT held:

“the interior face of the building means, the interior face of the structure of the building rather than the top surface of whatever is fixed to the structure of the building.”

In Fisher, tiles and waterproofing located above a structural slab were generally treated as lot property.

Harris J expressly rejected that approach.

Her Honour held that:

  • “interior face” refers to the interior face of the building, not the structural slab;
  • the visible completed surface is the relevant reference point;
  • the reasoning in Fisher incorrectly focused on the structural slab rather than the completed building surface; and
  • section 132 of the OCA does not support the proposition that everything attached above a structural slab automatically forms part of a lot.

Notwithstanding the above, the Court also reinforced the relevance of the benefit principle.  Although the balcony floor components were found to be common property, the Court noted that repair expenditure may nevertheless be recoverable from a benefiting owner pursuant to sections 24 and 49 of the OCA.

Which owners corporations are affected?

Notwithstanding the above, the decision is likely to have limited application to plans of subdivision registered after 2011. A significant feature of the dispute was that the relevant plan used “interior face” without being properly defined.

Since 2011, certainty has been provided by the Subdivision (Registrar’s Requirements) Regulations 2011 and, subsequently, the Subdivision (Registrar’s Requirements) Regulations 2021. Regulation 10(4)(a) now expressly provides that an “Interior Face”:

“lies along the interior face of any wall, floor (upper surface of elevated floor if any), ceiling (underside of suspended ceiling if any), window, door or balustrade of the relevant part of the building and any internal coverings, waterproof membranes and fixtures attached to walls, floors, and ceilings are included within the relevant parcel“.

Accordingly, while Damjanovski is now the leading authority concerning the interpretation of pre-2011 plans containing “interior face” notations, its broader application to plans governed by the 2011 and 2021 Regulations is limited.

What does Damjanovski mean for future balcony repair disputes?

There is now inconsistent interpretation of “interior face” notations in plans registered before and after 2011, which leads to uncertainty regarding the ownership of building elements and responsibility for their repair and maintenance, which should be consistent.

The practical significance of Damjanovski is that it challenges a number of assumptions regarding the ownership and maintenance of balcony floor systems in Victorian Owners Corporations.

For plans of subdivision registered prior to 2011 which utilise “interior face” notations, the decision provides strong authority that balcony floor systems, including tiles, waterproof membranes and screed, may constitute common property rather than lot property.

Importantly, Owners Corporations and managers should not assume that responsibility for balcony waterproofing rests with the lot owner simply because the balcony is attached to, or exclusively used by, that lot. Rather, the starting point must always be a careful examination of the relevant plan of subdivision to determine the location of the boundary between lot property and common property.

Despite the Court’s finding that the balcony floor components were common property, Damjanovski also confirms the continuing importance of the benefit principle. Owners Corporations should remember that ownership of an asset and liability for the cost of repairing that asset are separate questions. Even where works relate to common property, sections 24 and 49 of the OCA may permit costs to be allocated to a particular lot owner where the works are undertaken wholly or substantially for the benefit of that lot.

Accordingly, the decision is unlikely to eliminate disputes concerning balcony repairs. Rather, future disputes are likely to focus on two separate issues:

  1. whether the relevant building element forms part of common property or the lot; and
  2. if the element is common property, whether the cost of repair should be borne wholly or predominantly by a benefiting lot owner under the benefit principle.

Subject to any appeal, Owners Corporations and managers should carefully consider the implications of Damjanovski when determining responsibility for balcony repairs and associated costs and to seek legal advice for plans of subdivision registered prior to 2011.

 

If you require guidance on the impact of Damjanovski or responsibility for balcony repairs under your plan of subdivision, please contact the Victorian Grace Lawyers strata team at enquiries@gracelawyers.com.au or 1300 144 436.

 

Written by Leila Idris, Partner, and Christopher Oster, Special Counsel, Grace Lawyers

 

 