High Court of Australia Makes a Landmark Ruling in Favour of Strata Schemes in Building Defect Claims
NSW
The High Court of Australia finds that a builder/developer can no longer rely on a proportionate liability defence in building defect cases.
In a landmark win for consumer rights, a majority of the High Court of Australia handed down its judgment in Pafburn Pty Ltd & Anor v The Owners – Strata Plan No 84674 [2024] HCA 49 (Pafburn) on 11 December 2024. This decision has rebutted any aspirations that might be held by a builder or developer (as defendant/s) in relying upon a proportionate liability defence under Pt 4 of the Civil Liability Act 2002 (NSW) (CLA) in response to a claim for a breach of their duty to exercise reasonable care to avoid economic loss caused by defects made against them by an Owners Corporation pursuant to s.37(1)of the Design and Building Practitioners Act 2020 (DBPA) (together the Acts).
The particulars of Pafburn involved a builder and developer who sought to reduce their commercial exposures by seeking to attribute proportionate blame upon nine other parties involved in a strata scheme’s design and construction. The builder and developer asserted that such a defence was possible through the operation of the Acts. Grace Lawyers, in its second building and construction matter to come before the High Court of Australia, acted on behalf of the Owners Corporation to successfully argue that the proportionate liability scheme under Part 4 of the CLA did not apply to claims for breach of the statutory duty within the DBPA when raised as a defence by the builder or developer.
The decision is a welcome relief for Owners Corporations across NSW – mirroring the protections already afforded to homeowners and owners corporations under the Home Building Act 1989.
Why the decision is significant
Pafburn is significant because it closes down what was, until now, believed to be one of the largest defensive weapons in the defendant arsenal pertaining to claims under the DBPA – being the proportionate liability scheme under Part 4 of the CLA.
The proportionate liability regime, in effect, if it were not rebutted by the High Court, would allow a builder or developer to claim that anyone else involved in the construction was to an extent responsible for the damage and therefore attribute an amount to that party (or more than one named party). This defence, naming other “concurrent wrongdoers” – would seek orders from the Court that the amount of damages be reduced from the builder or developer to instead be payable by the introduced concurrent wrongdoers, based on their respective degree of culpability. In other words, the defendant sought to say that “if the court determines that I am at fault, then I reduce my degree of culpability by introducing that it is also the fault of named others to certain extents, also (attributed amounts).”
Practically (and previous to the Pafburn decision), this would mean that the Owners Corporation would sue the builder and developer responsible for the construction of the building only for the builder and developer to defend those proceedings by means of seeking an apportionment of liability against concurrent wrongdoers under the CLA that it would name. Thereafter, it would be for the Owners Corporation to determine which, if any, of the alleged concurrent wrongdoers they would seek to join to the proceedings and they would bear the cost, time, effort and risk of running claims against all parties.
For example, in a claim brought by an Owners Corporation against a builder for $1 million in damages arising from defective waterproofing, the builder might name any of the following parties as concurrent wrongdoers:
- The waterproofer who performed the work;
- The principal certifying authority who issued an occupation certificate despite the defective work; and
- The engineer who prepared the hydraulic blueprint for the building.
This could lead to a situation where the Court, accepting all four parties are responsible to some extent, “apportions” the damages amongst them accordingly.
The difficulties created by the proportionate liability regime for plaintiffs (particularly Owners Corporations) include the following:
- The possibility of some parties being insolvent. This is particularly prevalent in modern developments where companies are set up as special purpose vehicles for the duration of a development, before being put into liquidation afterwards;
- The fact that the plaintiff ‘bears the risk’ of not joining a party to the claim once they have been nominated as a wrongdoer. If the Court finds that a non-party is liable for a portion of the loss claimed, the plaintiff is simply disentitled to that amount. This means that an Owners Corporation, when faced with a proportionate liability defence, is required to make an independent assessment of whether the party can or even should be joined to the claim. This is particularly onerous in the case of owners corporations, who are not privy to the contractual arrangements between parties involved in the building work before its time. As a result, these assessments are often conducted on nothing but the strength of the defendant’s pleading;
- Commerciality concerns. Circling back to our example of the owners corporation with the defective waterproofing, let’s say the owners corporation is successful in obtaining $1 million in damages against the defendant waterproofer (who is found 100% liable). The builder, certifier and engineer are found not to be liable to any extent; and
- The claims against concurrent wrongdoers may be out of time.
The decision in Pafburn now means that an Owners Corporation can commence a claim against a builder/developer for a breach of the s.37(1) of DBPA (if the duty of care is established) and make the builder/developer personally liable for the whole of the economic loss caused by their breach (if both causation of loss by the breach and the amount of the loss are also established).
The builder/developer will no longer be permitted to file a proportionate liability defence and thereby the Owners Corporation no longer has to make the forensic decision of joining and pursuing any concurrent wrongdoer/s. The resulting situation post Pafburn is that the burden will be on the builder and developer to cross-claim against these other persons who they allege breached any applicable duty of care owed to them and they will have to incur the time, expense and risk of running these cross-claims.
In reaching its conclusion, the High Court affirmed that under the DBPA:
- if the plaintiff fails to establish the alleged breaches by the main contractor and/or developer, then the defendant/s will not be found liable at all for the claimed loss;
- if the plaintiff establishes such alleged breaches but fails to establish that those breaches caused the whole of the claimed economic loss, the defendant/s will be found liable only to the extent that their breaches caused the loss; and
- to the extent that the defendant/s are found liable to the plaintiff ss 37(1) and 39 of the DBPA do not prevent them from cross-claiming against other persons who they allege breached any applicable duty of care owed to them.
The decision confirms the onus upon the plaintiff under the DBPA to carefully formulate its claim, including the parties it seeks to recover from, alongside establishing that the duty of care exists, the duty has been breached, and (finally) the proportion it seeks to recover from the identified defendants.
Including Pafburn, Grace Lawyers and its partner Daniel Radman have acted for Owners Corporations in a number of leading decisions including the High Court matter of Brookfield Multiplex Ltd v. Owners Corporation Strata Plan 61288 & Anor [2014] HCA 36 and the NSW Court of Appeal matter of Rialto Sports Pty Limited v Cancer Care Associates Pty Limited; CCA Estates Pty Limited; Davjul Holdings Pty Limited; Armmam Pty Limited [2022] NSWCA 146.
If you require advice about your particular circumstances or claim involving the construction of your building, please contact any of our senior building and construction team members: Daniel Radman, Jessica Bates, Colin Grace or Paul Berrill on 1300 144 436.
NSW Supreme Court Rules in Favour of OC for Unapproved Works to Common Property
NSW
20 February 2025: Colman v The Owners – Strata Plan 61131 [2025] NSWSC 63.
Grace Lawyers was recently successful in the NSW Supreme Court in defending an owners corporation against a large claim made by a lot owner for unauthorised common property works. In deciding in favour of the owners corporation, the Court clarified how the various maintenance, approval and compensation provisions worked together under the Strata Schemes Management Act 2015 (NSW).
The issues that were decided in the owners corporation’s favour were:
- A lot owner cannot recover as damages (either prospectively or retrospectively) under Section 106(5) of the Strata Schemes Management Act 2015 (NSW) the cost of common property works undertaken without the approval of the owners corporation or an order of the Tribunal;
- Generally speaking, an owners corporation is not to be taken to have refused an application for approval to carry out common property works without having first considered it by motion at a general meeting (or strata committee meeting where appropriate);
- The Tribunal is not empowered to make an order approving common property works without those works first having been considered and refused by an owners corporation at the appropriate meeting.
The owners corporation had originally arranged for repairs to be carried out by a contractor to address a water leak emanating from a rooftop terrace. Without approval of the owners corporation, the lot owner made separate arrangements with the contractor to renovate the terrace area (including carrying out further common property works) and then sought to recover the substantial cost from the owners corporation as damages under Section 106(5) of the Strata Schemes Management Act 2015 (NSW). The lot owner argued that the required common property rectification works were more extensive than what the owners corporation had originally arranged and so he should be entitled to recover the cost of that work as well as lot property “repairs”.
Before commencing proceedings, the lot owner submitted an incomplete building application to retrospectively approve the renovation works at strata committee level. That application was refused on the basis that the strata committee did not have the power to approve the work (the work could not be classified as minor renovations). Subsequently, during the proceedings, the lot owner argued that an existing common property by-law in respect to other roofing works should be extended to apply to his rooftop terrace works.
The Tribunal initially dismissed the claim on the basis it was not satisfied that the waterproofing and tiling works claimed as compensation were for the purpose of rectifying a defect in the common property rather than forming part of the lot owner’s planned terrace renovation works. Accordingly, the cost of the renovation works (including the common property works) could not be awarded as “damages” under Section 106(5) of the Strata Schemes Management Act 2015 (NSW). The Tribunal also found that it could not make an order retrospectively approving the works under section 126(2) of the Strata Schemes Management Act 2015 (NSW) on the basis that an owners corporation must first refuse consent before the Tribunal could make such an order. Finally, the existing common property rights by-law did not apply as it was not passed for the purposes of the lot owner’s renovation works. The Tribunal’s decision was confirmed on appeal to the Appeal Panel.
On further appeal to the NSW Supreme Court, the Justice confirmed the correctness of the earlier decisions and made additional findings as follows:
- Where approval has been sought by way of special resolution and a common property rights by-law, an application for unreasonable refusal can be made under Section 149 (in respect to the common property rights by-law) and Section 126(2) (in respect to approval of the common property work);
- An owners corporation can undertake repairs to common property without needing to have passed an ordinary or special resolution. An owners corporation can also authorise a lot owner to carry out such repair works via the same process;
- Retrospective approval can be given to common property works by an owners corporation (under Sections 108, 110, and, where appropriate, 106) and the Tribunal under Section 126(2);
- The Tribunal is not authorised to make an order permitting common property works under Section 126(2) unless approval had first been sought from the owners corporation (and refused);
- For repairs to common property, this refusal of consent commonly takes the form of the owners corporation not passing a special resolution for the works at a general meeting, but in certain circumstances, an owners corporation could be found to have acted in a way that constitutes a constructive refusal of consent, even though it has not made a formal decision to refuse to approve the works at a general meeting.
- Damage/compensation cannot be awarded under Section 106(5) for common property works that had not been approved in the required manner (retrospectively or prospectively).
This decision highlights the crucial role of an owners corporation in controlling and approving works on common property and that lot owners cannot circumvent the process by carrying out works without approval and then seeking to recover the cost of carrying out the work later as “damages” under Section 106(5) of the Strata Schemes Management Act 2015 (NSW). It is also part of a number of recent NSW Supreme Court decisions defining the limits of damages claims under Section 106(5), and that such claims are not a “blank cheque” against an owners corporation.
Written by Peter Ton, Partner, and Andrew Stojanovic, Senior Associate, Grace Lawyers
If you require guidance in relation to unauthorised common property works, contact our NSW team at Grace Lawyers on 1300 144 436.
Disclaimer: This article is for informational purposes only and does not constitute legal advice. Readers should obtain independent legal advice on their specific legal issues.
Strata Living and Short Term Rentals: Understanding the Rules
NSW
Did you know that simply owning a strata property gives you the opportunity to create a profitable business and earn a passive income? Short-term rental accommodation, also known as short-term letting, is defined under section 54A of The Fair Trading Act 1987 (FTA), as:
“A commercial arrangement for giving a person the right to occupy residential premises for a period of not more than 3 months at any one time, and includes any arrangement prescribed by the regulations to be a short-term rental accommodation arrangement.”
Short-term letting has been used as a way to gain monetary benefit from an under-utilised asset. The easiest way to short-term let your strata property is through sites such as Airbnb, StayZ or Booking.com, however, you must consider the relevant sections of the Strata Schemes Management Act 2015 (NSW) (SSMA) before listing your property on one of these sites.
This article explores the laws surrounding short-term letting, focusing on whether the SSMA, tenancy agreements, or strata by-laws can restrict tenants and landlords from offering their property for short-term rentals.
Can tenants short-term let?
The case of Abdel-Messih v Azzi [2017] NSWCATAP 86 considered whether a landlord was entitled to terminate a tenant’s lease because they had sub-let the whole of the premises to short-term guests without permission.
In 2016, a landlord leased his Sydney CBD apartment to a tenant pursuant to a residential tenancy agreement for a term of one year. Clause 32 of the agreement stated:
“the landlord and tenant agree that… the tenant may, with the landlord’s written permission … sublet the residential premises, and … the landlord may refuse permission (whether or not it is reasonable to do so) to the … subletting the whole of the residential premises”.
Eight days after the commencement of the agreement the tenant began entering into sub-leases for the apartment for a period of three months, with various persons. In mid-2016 the landlord believed the tenant had sub-let the whole of the premises, without consent, breaching clause 32 of the agreement. The landlord then issued two termination notices. The terms of the sub-leases were also problematic, listing the tenant as the ‘landlord’ and sub-tenants as the ‘tenants’.
The New South Wales Civil and Administrative Tribunal (NCAT) found that the tenant had breached the agreement by sub-letting the premises without the landlord’s permission and that the serious nature of the breach, which exposed the landlord to risks beyond what he voluntarily accepted, justified the termination of the agreement and made an order to that effect.
Consequently, if you are renting a strata property, it is your principal place of residence and you wish to sub-let or list it on a site for short-term rental accommodation, it is vital you consult your lease, otherwise you may be in breach of its terms.
Case spotlight: Estens v Owners Corporation SP 11825 [2017] – Validity of by-laws prohibiting short-term letting
The case of Estens v Owners Corporation SP 11825 [2017] NSWCATCD 63 considered whether a special by-law passed by the Owners Corporation prohibiting short-term letting was valid.
In 2016, a landlord rented out her unit through Airbnb. She received multiple complaints related to the Airbnb guests misuse of common property and because of this, in 2017, the Owners Corporation passed a special by-law prohibiting short-term letting, meaning listing units on Airbnb for short term rental was now illegal.
The landlord then sought an order from the New South Wales Civil and Administrative Tribunal (NCAT), relying on a notation from the New South Wales Fair Trading published November 2016 that indicated “no by-law is capable of restricting a dealing in a lot including restricting short-term letting”. The Owners Corporation argued that nowhere in the SSMA permitted the use of sights such as Airbnb, for short-term letting.
The Tribunal ultimately found that the Airbnb tenancy was sufficient to constitute a tenancy or lease, as there was a specific commencement date, end date and during the time the guest was living there they have exclusive use of the property. Hence, the Tribunal held that the by-law was invalid as the Owners Corporation had no power to pass such a by-law by reason of the operation of section 139(2) SSMA.
As a result of the case law, the Strata Schemes Management Act was amended to include:
Section 137A Short-term rental accommodation
- A by-law made by a special resolution of an owners corporation may prohibit a lot being used for the purposes of a short-term rental accommodation arrangement if the lot is not the principal place of residence of the person who, pursuant to the arrangement, is giving another person the right to occupy the lot.
- A by-law has no force or effect to the extent to which it purports to prevent a lot being used for the purposes of a short-term rental accommodation arrangement if the lot is the principal place of residence of the person who, pursuant to the arrangement, is giving another person the right to occupy the lot.
Commencing on 10 April 2020, section 137A allowed the Owners Corporation to create by-laws, via special resolution, to prohibit a lot from being used for the purposes of a short-term rental accommodation arrangement, if the lot was not the principal place of residence of the host. Therefore, if you are the owner of a strata lot and it is your principal place of residence, you are permitted to short-term let that property on sites such as Airbnb, StayZ or Booking.com.
If you live in a strata property with by-laws that prohibit short-term rental accommodation or letting, it is important to seek legal advice on their validity.
NSW Government introduces a mandatory Code of Conduct for short-term letting
In December 2020 the NSW government introduced a mandatory Code of Conduct for the short-term rental accommodation industry. The Code contains obligations for booking platforms, guests, hosts, letting agents and sets out requirements and standards of behaviour for participants. If a participant is in breach of the Code there are disciplinary actions that NSW Fair Trading can take, which include listing any non-compliant participants on an Exclusion Register.
Please find a link to the Code of Conduct here.
Conclusion
Short-term rental accommodation presents an appealing opportunity for property owners to transform their assets into profitable ventures and generate passive income. However, success in this field requires compliance with local laws, strata by-laws and regulatory measures, including registration and adherence to fire safety standards, otherwise your venture may turn into a financial liability. By staying informed property owners can maximise their returns while minimising risks. With proper preparation, short-term rentals can be a smart and rewarding business move for property owners.
Written by Anna Hahm, Partner, and Catia Pieriboni, Lawyer, Grace Lawyers, NSW
Please contact the NSW Strata and Property team at Grace Lawyers for any assistance in drafting by-laws or advice on Strata matters on 1300 144 436.
Disclaimer: This article is for informational purposes only and does not constitute legal advice. Readers should obtain independent legal advice on their specific legal issues.
Owners Corporations can Provide for Cost Recovery within By-Laws
NSW
Gokani-Robins Pty Ltd v The Owners – Strata Plan No 77109 [2025] NSWCATAP 107
In a significant decision for NSW strata law, the NSW Appeals Panel has upheld the ability of strata schemes to include cost recovery clauses within a by-law. Successfully argued by Grace Lawyers, this case confirmed that a cost recovery clause in a by-law is valid and enforceable for legitimate purposes so long as is has been reasonably and appropriately drafted.
What the Fire Safety By-Law Required
The dispute involved a fire safety by-law that provided for the following:
- imposed a number of restrictions and obligations on owners and occupiers, including:
- not to interfere with, impede or affect, the operation of the owners corporation’s fire safety services or reduce the level of fire safety for individual lots or the strata scheme as a whole, and/or
- not to trigger false fire alarms that caused the fire brigade or any other authority, service provider or other person to tend the false alarm, and
- required owners and occupiers to provide access to the owners corporation
- allowed the owners corporations to investigate and receive reports on false alarms, call outs and provision of services related to the fire safety services to determine who is responsible for causing them;
- provided for owners and occupiers to indemnify the owners corporation for any claims, charges, and costs arising from false fire alarms caused by negligence/omission of the owner/occupier in relation to false fire alarms, the failure to give access, or the breach of the by-law;
- provided for the owners corporation to issue demands on the owner or occupier for the payment of these claims, charges and costs on one months’ notice and if not paid, the right to recovery of those claims, charges and costs in a Court or Tribunal of competent jurisdiction
- a default provision that allowed the owners corporation to demand that the defaulting owners or occupiers remedy their default and the ability of the owners corporation to remedy the default itself.
The Legal Challenge
The property owners applied to the Tribunal at first instance for an order for the fire safety by-law to be declared invalid on the grounds that the by-law was harsh, unconscionable, and/or oppressive, pursuant to section 150(1) of the Strata Schemes Management Act 2015 (NSW). Their challenge came after the owners corporation had commenced legal action in the Local Court to recover false fire alarm charges under the by-law. The case was heard at first instance by Senior Member Woods.
The property owners argued that multiple sections of the by-law were harsh, unconscionable, and/or oppressive, because:
- The by-law, in practice, would prevent the property owners from doing anything that would have a positive effect on the operation of the owners corporation’s fire safety services;
- The by-law did not specify the amount of notice to be provided by the owners corporation before entering the property or require the owners corporation to provide the details of the outcome of inspection, testing repair or replace the fire safety services;
- The by-law did not provide that the owners corporation had to commence legal proceedings to claim the indemnity against an owner or occupier, the power to recover costs was unfettered regardless of reasonableness, and the by-law made no reference to a Court or Tribunal having to consider the amount claimed nor inform the owner or occupier of the basis of the claim.
- The power of the owners corporation to investigate and receive reports under the by-law was unbalanced, a conflict of interest, procedurally unfair and does not preserve use or enjoyment of life of the strata scheme and its owners.
- The power under the by-law to issue a demand on an owner or occupier for the claims, charges and costs or recover them was invalid because the Tribunal had declared invalid another by-law for the recovery of enforcement costs in a separate decision involving the property owners and the owners corporation.
- The default provision of the by-law allowed only the owners corporation to decide what is to be done, whether the work is necessary and whether the way the work is to be carried out was reasonable.
The Tribunal did not agree with the lot owner’s interpretation of the by-law and dismissed its application. The Senior Member found the by-law was not harsh, unconscionable, or oppressive or otherwise invalid, for the following reasons:
- The restrictions and obligations on the owner or occupier only prevented them from doing something that interfered with or otherwise negatively impacted the fire safety services.
- It was implied in the by-law that the owners corporation was required to give sufficient notice before entering a lot to inspect, test, repair, or replace the fire safety services and as it is ultimately responsible for the fire safety services, the owners corporation is not required to provide the details of the outcome of the investigations, tests, repairs or works to the owner or occupier.
- The requirement of the owners or occupiers to indemnify the owners corporation for costs, expenses and charges incurred because of an act, negligence, or omission was subject to the indemnity only being recoverable in a Court or Tribunal of competent jurisdiction. The Court or Tribunal would then determine the reasonableness of those costs, expenses and charges sought under the indemnity.
- The owners corporation, in the first instance, being able to investigate and determine who is responsible for false alarms, call outs, or services was for the benefit of the owners of the strata scheme as a whole and individually, because it allowed the owners corporation to make an informed determination before taking action.
- The owners corporation being able to demand and take legal action to recover payments due under the by-law is subject to the owners corporation waiting at least a month after issuing the demand before taking such action and the right of recovery of payments and a Court or Tribunal determining the reasonableness of those payments;
- The owners corporation being able to require an owner or occupier to rectify a breach of the by-law and take action itself to rectify the breach is necessary for the proper operation of the rest of the by-law.
Appeal Panel Confirms Legitimacy of Fire Safety By-Law and Costs Recovery
The owners corporation was successful in defending against an “all grounds” appeal of the decision to the NCAT Appeals Panel. In dismissing the appeal, the Appeal Panel confirmed a number of important principles that apply when considering a challenge to a by-law, including the cost recovery portion, on the alleged basis that the by-law is harsh, unconscionable, and/or oppressive under Section 150 of the Strata Schemes Management Act 2015 (NSW). Those include the power of an owners corporation to make by-laws is not limited to or confined by what is provided for in the strata legislation or model by-laws, and that by-laws should be construed to preserve their validity where possible.
Ensuring the Validity of Cost Recovery By-Laws Through Careful Drafting
The case confirms the importance and usefulness of cost recovery clauses in by-laws in appropriate cases and where they have been properly drafted. Although the recent climate has been to consider all by-laws susceptible to being set aside, the decision demonstrates the importance of making sure by-laws are prepared carefully and in a manner suitable for the specific purpose of the strata scheme. Boilerplate or ‘insert here’ style by-laws are often the ones that are challenged and then set aside as invalid.
Implications for NSW Strata Communities
This decision reinforces that owners corporations have broad powers to implement by-laws for building safety, even when those by-laws impose significant obligations and potential costs on owners. However, the case also demonstrates the critical importance of including appropriate safeguards and judicial oversight for cost recovery.
Written by Peter Ton, Partner, and Andrew Stojanovic, Senior Associate, Grace Lawyers
If you require guidance on drafting by-laws, contact our Grace Lawyers team on 1300 144 436.
Disclaimer: This article is for informational purposes only and does not constitute legal advice. Readers should obtain independent legal advice on their specific legal issues.
Harnessing Solar Energy: Opportunities and Considerations for Strata Schemes
NSW
Considering solar panels in your strata property? You’re not alone! With rising energy costs and growing environmental awareness, many Australians are turning to solar power to save money, reduce emissions and embrace renewable energy. If you live in a strata scheme, installing solar panels involves navigating specific legal requirements. This article outlines everything you need to know—from relevant legislation, case law and by-laws to the practical costs and long-term benefits of solar panel installation.
How do I go about installing solar panels in a strata property?
The installation of solar panels for a unit in a strata scheme requires approval from the strata committee as solar panels involve a structural change to the building. To obtain approval for solar panel installation requires a simple majority, being over 50% of owners to vote in favour of the ’sustainability infrastructure resolution’ at a general meeting. A by-law for solar panel installation will also need to be approved, as the solar panels are likely to be installed on a common property roof.
Is government funding available to a strata scheme?
The 2021 Australian Census revealed that 21.7% of people in NSW live in apartments or flats and less than 2% of apartment buildings in NSW have installed solar. Given energy costs continue to climb and the number of people living in apartments, or renting, continues to increase, innovative solutions are required for apartment owners to benefit from solar energy.
As such, the NSW government has launched an initiative enabling Owners Corporations to apply for funding to install shared solar panel systems on residential buildings. The grants are available for apartment residents and will fund 50% of the cost of the shared solar system, in any eligible residential apartment buildings or multi-unit dwellings. There is $25 million in grant funding available, with up to $150,000 per project. This will add value to homes and help residents, including renters, reduce their energy bills and greenhouse gas emissions.
Applications for this grant will close at 5:00pm on 1 December 2025, or earlier if the funds have been fully allocated. Please find the Grant guidelines here:
NSW Government Grants—Solar Apartment Residents
What are the advantages of solar panels?
There are a number of advantages to installing solar panels in a strata building including:
- Reduced electricity/energy costs: solar panels can lower electricity bills for the entire strata scheme as residents can use the solar energy generated as opposed to relying solely on the grid.
- Environmentally friendly: solar energy is a clean and renewable energy source that reduces carbon emissions.
- Increased property value and positive public image: installing solar panels may increase the value of the strata building because it showcases commitment to sustainability making it more attractive to potential purchasers or renters.
- Energy independence: solar panels may provide a degree of energy independence, which can protect the strata scheme from rising electricity prices and electricity grid outages.
- Easily shared: it is easy to share solar energy now, however not every owner has to participate. A shared solar system can be installed for just those owners who are interested.
- Embedded network: a shared energy system that distributes solar power across units, removing the need for separate solar providers.
What are the disadvantages of solar panels?
Whilst there are numerous advantages of solar panel installation for a strata scheme, there are also drawbacks which need to be considered before installation:
- Costs: the initial investment for purchasing and installing solar panels can be significant, though, a strata scheme may wish to access the government funding available as mentioned above.
- Strata approval: obtaining approval from owners may be challenging as some owners may be hesitant due to cost concerns, aesthetic preferences or negative media they have viewed regarding solar panels.
- Roof space: the amount of roof space may limit the number of solar panels that can be installed, affecting energy savings and providing challenges such as the fair allocation of roof area between units. The amount of roof space and physical characteristics will also have to be considered when choosing a model for solar for the building.
- Maintenance and repairs: solar panels require periodic maintenance which can add to the cost, however, this is the same for the regular electricity grid.
- Cost of battery storage: batteries may cost up to $13,000.00, but without them solar energy can only be used while the sun is shining, which doesn’t align with typical energy usage, as peak usage is in the evening between 6:00 pm to 9:00 pm. The Government launched the Cheaper Home Batteries Program on 1 July 2025, which the Owners Corporation may consider to support the cost-effectiveness of shared solar infrastructure.
To learn more, visit: Labor to deliver one million energy bill busting batteries
Unreasonable refusal: NCAT decision in favour of owner’s right to solar
Laws v The Owners—Strata Plan 97230 [2022] NSWCATCD 131
The case of Laws v The Owners—Strata Plan 97230 considered whether the Owners Corporation unreasonably refused to create a by-law permitting the installation of solar panels on common property.
Ms Laws, the owner of a lot in a strata scheme in Ettalong, wished to install solar panels on the roof of her unit. There was no dispute that the roof was common property or that she required the consent of the Owners Corporation to install the panels, and she proposed that the Owners Corporation approve a by-law to enable her to install the panels. As solar panels are sustainability infrastructure, the motion would pass so long as less than 50% of owners opposed the motion. This amendment to the SSMA was introduced to reflect the importance of sustainability infrastructure to the broader community.
A meeting was held and two motions proposed. Motion 13 sought consent to the installation of the panels and Motion 14 sought that the Owners Corporation create a by-Law to enable the installation of the panels. Both Motion 13 and 14 were defeated, as several owners refused. Ms Laws claimed that the Owners Corporation’s refusal to approve the by-law and provide consent to her request was unreasonable because no reasons were given, none were recorded in the minutes of the meeting and she could not successfully communicate with members of the committee.
NCAT concluded that because the refusing owners did not account for the benefit of the proposal to Ms Laws, as set out in the motion, the decision was unreasonable. The owners came to the decision without considering all the material provided. And as they were invited to express their position prior to the meeting and vote by pre poll, there was no opportunity for discussion at the meeting.
Ultimately, NCAT held that the Owners Corporation’s refusal was unreasonable and made the orders sought by Ms Laws. In coming to this decision NCAT considered that:
“solar panels are increasingly found on rooftops, and objectively cannot be said to adversely affect the visual amenity of the scheme…there is no evidence that the installation of the panels will increase the insurance premiums…the proposed by-law appear(s) to adequately protect the Owners Corporation…and there are cost savings to the applicant and any other lot owner who might wish to seek to have solar panels on their roof”.
Conclusion
Whilst the initial cost and complexities of roof space and shared ownership can present challenges, the advantages of solar panels in strata, namely, reduced energy costs, increased property value and use of green energy, make solar panels a worthwhile investment. By weighing these factors and taking into account the available funding and case law, strata schemes are well-positioned to harness the power of the sun to create a more sustainable and economically beneficial future for all residents.
Written by Anna Hahm, Partner and Catia Pieriboni, Lawyer, Grace Lawyers NSW
Planning to install solar panels or other sustainability infrastructure in your strata scheme? Contact the NSW Strata and Property team at Grace Lawyers for expert advice and tailored by-law preparation. Call 1300 144 436.
Strata Legislation Update 2025: New Rules for Debt Recovery and Payment Plans
NSW
The Strata Schemes Legislation Amendment Act 2025 (the Amendment Act) was passed by the NSW Parliament on 18 February 2025. It contained sweeping changes to numerous sections of the Strata Schemes Management Act 2015 and the Community Land Management Act 2021. While some of these changes came into effect on 1 July 2025, NSW Fair Trading announced on 23 September 2025 that the bulk of the changes will commence on 27 October 2025 and others on 1 April 2026.
A key reform taking effect on 27 October 2025 involves updated provisions for debt recovery and payment plans under the Strata and Community Schemes legislation. The main changes include:
1. Levy Notices
- All levy notices must be accompanied by a Financial Hardship Information Statement.
2. Payment Plans
- An owners corporation and an owner may agree to a payment plan for the payment of overdue contributions.
- A payment plan is limited to a period of 12 months but a further plan may be agreed to.
- An owners corporation must not, by resolution, refuse to enter into payment plans for the payment of overdue contributions.
- An owners corporation may refuse to enter into payment plans for the payment of overdue contributions in particular cases.
- A request by an owner to enter into a payment plan (the request) may be reasonably refused by the owners corporation.
- The Regulations will prescribe what constitutes a reasonable refusal in relation to payment plans.
The Regulations may include:
- The main reason to reasonably refuse a payment plan is whether the non-payment of levies by that owner will specifically result in a deficit to the administrative or capital works fund or that such a deficit will result in a failure of the owners corporation to comply with its obligations to repair and maintain common property.
- When proposing a payment plan, a lot owner must submit their proposal to the owners corporation using the basic payment plan form prescribed by the Regulations.
- The owners corporation or the committee of the owners corporation must determine a payment plan request and provide its written decision to the lot owner within 28 days after receiving the payment plan form.
- Any payment plan request that is refused must include written reasons for the refusal and why those reasons apply in that specific instance.
- The owners corporation must not request the owner to provide information or evidence in support of a request other than the information set out in the prescribed form.
- An owners corporation cannot charge a payment plan fee or any other charge related to making or entering into a payment plan.
- A lot owner may apply to the Tribunal to review an owners corporation’s refusal of a proposed payment plan.
3. Debt Recovery Action
- An owners corporation may only take action to recover the reasonable expenses of the owners corporation incurred in recovering unpaid contributions and any interest payable on unpaid contributions if the owners corporation has offered the owner the option of entering into a payment plan for the payment of the unpaid contributions, and pursuant to an order of the Tribunal or a court.
- An owners corporation must not pursue recovery of levies, interest or costs while the amount is subject to a payment plan that the owner is complying with.
4. Payment Allocations
- All payments must be applied as directed by the lot owner or if ordered by a Court or Tribunal.
- Otherwise all payments by a lot owner must be applied in the following order:
- Levies (oldest first); then
- Interest; then
- Costs
5. Debt Recovery Proceedings
- Recovery proceedings for arrears must not commence without providing the debtor at least 30 days’ notice—an increase from the previous 21-day requirement.
Summary
Significant reforms to strata debt recovery in NSW will take effect from 27 October 2025 under the Strata Schemes Legislation Amendment Act 2025. Key changes include mandatory hardship information with levy notices, stricter protocols for offering and refusing payment plans and clearer procedures for plan approval. Owners corporations must provide 30 days’ notice before commencing recovery proceedings and cannot pursue debts while a compliant payment plan is in place. These reforms aim to enhance fairness, transparency and financial accountability.
Written by Daniel Radman, Partner, Grace Lawyers NSW
About Grace Lawyers
Grace Lawyers is the leading provider of strata debt recovery services to owners corporations in New South Wales.
Daniel Radman along with Caroline Yung, National Manager – Debt Recovery, oversee all aspects of the debt recovery practice at Grace Lawyers. Daniel is a leading lawyer in strata debt recovery where he acts exclusively for owners corporations. He has practised in the field for over 20 years, regularly delivers seminars to the industry on strata debt recovery, contributes to government reform in the area (including his participation in the NSW Fair Trading round table debt recovery reform process) and has also led and advocated in prominent strata recovery cases in all Courts and Tribunals including matters on appeal.
Should you wish to discuss any aspect of the latest changes to debt recovery and payment plans, please feel free to contact either Daniel or Caroline on 1300 144 436.
When Developer Control Derails a Defect Claim: The Road to Compulsory Management
NSW
Strata schemes can run into serious trouble when voting power and legal conflicts collide. This article explores allegations that a developer‑controlled majority disrupted a building‑defect claim, overturned key resolutions and ultimately left an Owners Corporation (OC) unable to act in its own interests. Through NCAT’s findings, strata managers can see how governance failures, ignored legal advice and entrenched conflicts of interest can push a scheme into dysfunction—and why compulsory management becomes the only workable circuit‑breaker.
Background
Birns & Ors v Querin & Ors (NCAT, 2025) is a textbook example of what can go wrong when developers keep a voting majority in a strata scheme—especially during a major building‑defect dispute.
The OC commenced building‑defect proceedings against the developer in 2023. An expert report estimated the cost of fixing the defects at $2.846 million. The developers’ expert, however, denied “37 of the 42 defects… amount[ing] to a denial of about 99% of the estimated cost of rectification.”
In an OC comprising 16 lots, the developer held nine lots and sold one lot to a related entity which in effect gave the developer an ‘effective majority’ control over 51% of the unit entitlement vote. Of the seven remaining lot owners, six separate lot owners collectively voted to commence and continue the defect case against the developer.
That imbalance of voting power became the centre of the conflict.
Up until about March 2025, the developer was excluded from any vote relating to the defect case pursuant to Part 3, Clause 11 of Schedule 1 of the Strata Schemes Management Act 2015 (the Act). However, this position changed and the developer was subsequently permitted to vote on resolutions pertaining to the defect case.
At a general meeting held in April 2025, the developers used their majority to:
- Void the earlier resolutions of the OC that resolved to fund the OC’s legal team and experts and advance the defect case ;
- Vote down attempts to reinstate those resolutions; and
- Pass new motions forcing the OC’s experts into conclaves with the developers’ experts, agreeing to the developers’ preferred timetable, and stopping all further legal steps until joint reports were produced.
Of the remaining seven lot holders, one lot owner voted with the developer while six others voted against the developer.
The Owners Corporation was Left Powerless
The OC’s lawyers provided strong legal advice about the adverse consequences of the developers’ actions at the general meeting. This included the OC’s legal representation and expert witnesses being defunded and the OC unable to even take the appropriate steps to comply with the resolutions of the developer to engage in conclaves and produce joint reports.
The OC’s lawyers warned that the developers’ voting power allowed them to in effect “negotiate with themselves” as both the controlling owners and the defendants in the defect case.
The NCAT matter
The six lot owners who voted against the developer at the general meeting commenced proceedings as applicants in the NCAT seeking orders for the appointment of a compulsory strata manager arguing that the OC had become dysfunctional. The combination of:
- developer control;
- cancelled legal funding;
- forced changes to litigation strategy; and
- the inability of the OC to act in its own interests
…created a situation where the OC could no longer operate and function properly.
The Applicant’s Case
The applicants argued the OC had become dysfunctional because the developers were using their voting majority to control decisions about the defect case even though they were the defendants in that case. This created what they described as a clear conflict of interest and effectively allowed the developers to “enter into settlement discussions with themselves”.
The applicants’ position was that the developers’ votes cut off funding for the OC’s lawyers and experts, leaving the OC unable to comply with Court orders, progress the proceedings or even act on the very steps the developers resolved at the general meeting, such as holding conclaves and preparing joint expert reports. The OC was “unable to even take the appropriate steps to comply with the resolutions of the developer.”
The applicants also pointed out that the developers passed a motion stopping the OC from taking any further steps in the Supreme Court proceedings until joint reports were completed—a hurdle that was impossible to clear without funding. Further, they argued that this behaviour was not in the best interests of all owners, contrary to section 9 of the Act, and clearly demonstrated dysfunction.
The Owners Corporation’s Case
The OC, the First Respondent in the NCAT matter (being represented by different lawyers to those in the defect case and who in effect were given instructions to defend the NCAT proceedings by the developer) argued that there was no dysfunction and therefore no need for a compulsory strata manager. They said that the developers were legally entitled to vote on all motions about the Supreme Court defect case, and the resolutions resolved by the developer at the general meeting were proper and allowed under the Act.
They also argued that concerns about the developers “self‑settling” was speculation. In their view, nothing the developers had done showed that the OC was failing to function.
The Developers’ Case
The developers raised a similar argument to that made by the OC.
They maintained that their voting decisions were rational and cost‑focused, not an attempt to “self‑settle,” and that they simply lacked enough information to approve funding for lawyers and experts. They also stated that the developers were willing to work with the OC and aimed only to “reduce unnecessary costs,” suggesting alternatives existed and a compulsory appointment was not justified.
Should a Compulsory Strata Manager be Appointed?
The Tribunal found that the conflict of interest created by the developers’ voting majority would continue throughout the Supreme Court defect proceedings, with no sign that their control will change. The developers had acted against strong legal advice, and offered no reasonable explanation for doing so, even though that advice warned that their voting decisions would “severely prejudic[e] the OC’s case.”
Because the dysfunction had already caused real harm—and was likely to continue—the Tribunal decided that appointing a compulsory strata manager was necessary to protect the OC and prevent further prejudice in the Supreme Court case.
The Tribunal ordered the appointment for 18 months, giving the defect proceedings time to run without interference from the conflict.
Summary
In Birns & Ors v Querin & Ors (NCAT, 2025), the Tribunal examined how a developer‑controlled voting majority disrupted an owners corporation’s ability to run a major $2.846 million building‑defect claim. The developers overturned key resolutions, blocked legal funding and acted against strong legal advice, creating ongoing conflict and dysfunction. To protect the owners corporation and prevent further prejudice in the Supreme Court proceedings, the NCAT made orders appointing a compulsory appointed strata manager to manage the OC.
Written by Daniel Radman, Managing Partner, and John Lim, Associate, Grace Lawyers
If your strata scheme is facing similar developer‑driven obstacles to pursuing building‑defect claims, contact our NSW Building and Construction team on 1300 144 436.
NSW Court of Appeal Confirms Builders Have No Automatic Right to Return and Rectify Defects
NSW
In the recent Court of Appeal decision of Ceerose Pty Ltd v The Owners – Strata Plan No.89074 [2025] NSWCA 235 the court upheld the long-established principal that the builder is not entitled to return to rectify their defects and confirmed that whether or not they should be allowed to return will always depend upon what is reasonable.
The case involved the “Eliza” building on Elizabeth Street in Sydney, overlooking Hyde Park and St Mary’s Cathedral which made headlines when completed in 2014 after the three-storey penthouse sold for a then record $15 million.
Does a builder have a right to return and rectify strata defects?
The Owners Corporation of SP 89074 served a 600-page expert report claiming more than 300 defects including urgent fire safety works, drainage, flooring and bathroom issues. The builder responded by agreeing to return to rectify nearly 100 of the defects and stating that they were always ready, willing and able to rectify any genuine defects.
This is common for a large builder because it is actually highly unlikely that there will not be any defects in a large building and it will always be much quicker and cheaper for a builder to rectify their own defects because they are familiar with their site and the products used. There is also always the danger that a new builder will charge more to rectify another builder’s defects and will often discover more problems.
This is partly why the NSW government, which is responsible for licensing builders, includes section 48MA in the Home Building Act such that:
“A court or tribunal determining a building claim involving an allegation of defective residential building work or specialist work by a party to the proceedings (the responsible party) is to have regard to the principle that rectification work by the responsible party is the preferred outcome”.
In NCAT, where the vast majority of these building claims are initially brought, the tribunal’s stated preferred position is for the original builder to return to rectify their own defects often by agreement or by an NCAT work order.
Can owners deny builder access to rectify defects?
There is however no actual “right” for the builder to return. After completion of the building it is owned by the Owners Corporation and they can determine who enters the site to do work. In the Eliza case, the owners decided they had lost faith in the ability or the willingness of the builder to return to adequately rectify the defects. This case was similar to other Supreme Court cases like SP 76674 v Di Blasio and Owners Strata Plan 89041v Galyan Pty Ltd. I previously had an NCAT case where the original builder still lived in the building and the other owners had all lost faith in his ability to rectify the building properly even though it was much cheaper than hiring a new builder.
Reasonable owners will generally allow the original builder back to rectify defects because it does not cost them anything and usually gets the building fixed. However if they keep having to beg the builder to return and everyone gets annoyed with each other and the defects still don’t seem to be getting fixed then the owners may have to commence legal proceedings because their statutory warranty rights are about to expire. At this point the goodwill of the builder can also expire.
What is an owner’s duty to mitigate loss in a building defect claim?
In the case of the Eliza building, there were two key issues that the Court had to determine. The first was the owners’ “duty to mitigate”. Where a Plaintiff is claiming loss against a Defendant they have to take reasonable steps to minimise their damage. That may include allowing the builder back to fix the defects if that was reasonable. Similarly the Plaintiff is not entitled to an upgrade. So if you buy a rundown old unit with chrome taps that don’t work, you can replace them but if you choose a solid gold fitting you cannot expect the original builder to cover the extra cost of the better product.
In the Eliza building after apparently a number of requests by the owners to the builder to rectify defects the owners advised the builder that they had lost confidence in the builder and that they were unwilling to let the builder have any further opportunities to repair the defects. The case was referred to a Supreme Court Referee who produced a report on liability issues as well as a report on the quantum of the cost to rectify the defects. The builder argues that the owners had failed to mitigate their loss because they had refused to allow the builder access to rectify the defects at no cost to the owners. The Referee concluded that the onus was on the builder to prove that the owner’s decision to deny access to them was unreasonable in all the circumstances. He concluded that the owners had not acted unreasonably in refusing access to the builder to carry out rectification.
The Supreme Court judge accepted the Referee’s report and entered judgment for the owners in the sum of $1.95 million. The builder appealed arguing that the judge made an error regarding the owner’s duty to mitigate their loss and also that there was a “positive obligation” on the owners to provide the builder with an opportunity to rectify the defects.
Who must prove that refusing access was unreasonable?
The key issue before the Court of Appeal was which party had to prove that the owners’ refusal to allow the builder to return was unreasonable. The builder argued that once they had raised the issue in their defence of the failure to mitigate then the onus of proof shifted to the owners to prove that their refusal to allow the builder to return was unreasonable. The Court of Appeal ultimately agreed with the owners and the court that the builder had the duty to prove that the owners had been unreasonable and that they had failed to establish that.
Why did the Court of Appeal rule in favour of the owners?
The builder had argued that the owners may have manufactured the argument of their loss of confidence in the builder because they preferred to get a lump sum award that they could use when and how they chose. The Court of Appeal referred to the previous cases and determined that there is not any special common law rule applicable to building contracts in this regard and that the owners were not required to demonstrate excessive diligence nor perfection.
As is so often the case it came down to what the court determined to be reasonable in all the circumstances and ultimately the builders failed to establish that the owners had been unreasonable.
What are the practical lessons for owners corporations and builders?
Key takeaways:
- There is no positive obligation on the owners to provide the builder with an opportunity to return to rectify their own defects;
- A refusal to allow the builder to return to rectify can be argued as a failure to mitigate the owners’ loss, but that is just the start of the argument. The builder has the onus to prove that the owner’s refusal of access was unreasonable;
- The onus did not shift to the owners to prove they were not unreasonable, the onus was always on the builder to prove that the owners were unreasonable;
- The Court of Appeal in analysing the evidence of the owner’s behaviour reiterated that in the case of a nil all draw in terms of evidence the party with the onus of proof (here the builder) had failed to prove the refusal was unreasonable and therefore they lost;
- It will be more difficult to prove that an Owners Corporation is being unreasonable because it is a collection of minds that has an obligation to do what is best for the whole Owners Corporation; and
- In most cases it will still be cheaper, quicker and easier to allow the original builder to return to rectify the defects.
Summary
In Ceerose Pty Ltd v The Owners – Strata Plan No. 89074 [2025] NSWCA 235, the NSW Court of Appeal confirmed that owners are not obliged to allow a builder to return and rectify defects. While rectification by the original builder remains the preferred outcome, owners may refuse access if that is reasonable in the circumstances. Importantly, the builder bears the burden of proving the refusal was unreasonable. The decision reinforces that each case depends on its facts and the standard of reasonableness.
If you require guidance on building defect claims, statutory warranty disputes, Owners Corporation rights, or construction litigation, please contact our Building and Construction team on 1300 144 436.
Written by Duncan Campbell, Building and Construction Partner, Grace Lawyers
Last updated on 23 July 2026