Major Win for Bodies Corporate: Direct Right to Pursue Builders Confirmed
QLD
When water leaks or defects appear in a new building, one of the first questions lot owners ask is whether their body corporate can take action against the builder—especially when the body corporate wasn’t a party to the original construction contract. For years in Queensland, bodies corporate have sued builders directly, but there has always been uncertainty about whether this was technically allowed. That uncertainty has now been resolved.
In the case of Body Corporate for Westmark Milton CTS 49024 v Devine Constructions Pty Ltd [2026] QSC 9 (27 January 2026), the Supreme Court of Queensland delivered a clear and significant answer. A body corporate can bring contractual claims in its own name. It does not need to include the original developer, even if the developer has no interest in the case or no longer exists. This is an important clarification for bodies corporate, managers and the entire strata sector.
Who can take action when defects appear in a new building?
The Westmark Milton development was constructed under a 2014 contract between the developer, Walker and Devine Constructions. When the scheme was established in 2016, the body corporate came into existence.
In 2017, after a significant rain event, water leaked into 53 lots. Westmark alleged defects in the common property and commenced legal proceedings against Devine in 2023. Because it wasn’t a party to the original building contract, it relied on section 36(3) of the BCCM Act, which says the body corporate becomes “subrogated to the rights of the original owner” under any pre‑establishment contract relating to common property.
Devine argued that the body corporate had to sue the builder in the name of the developer or include the developer as a party in the case.
Westmark disagreed. It asked the Court to confirm that the body corporate could bring the claim in its own name, without needing the developer involved.
Did the body corporate need the developer to sue the builder?
Devine (the builder) argued “subrogation” is a technical legal concept. Under that concept, a subrogated party (the body corporate) must sue in the name of the original claimant (the developer). Therefore, Westmark had to include the developer.
Westmark (the body corporate) argued that the BCCM Act is designed to give bodies corporate practical control over common property. The word “subrogated” in this context was meant to operate as a statutory transfer of rights, not a technical limitation. Requiring the developer to be a party to a case would undermine the BCCM Act’s purpose and cause unnecessary cost and delay.
What the court decided about the body corporate’s right to sue
Justice Ryan agreed with Westmark.
The Court held that, in this context, “subrogated” was not used in its technical legal sense. Instead, section 36(3) of the BCCM Act transfers the original owner’s contractual rights to the body corporate. The body corporate can enforce those rights in its own name.
There is no requirement to include the developer, even if the developer has no ongoing role or has ceased to exist.
The Court granted Westmark the declaration it sought and dismissed Devine’s summary judgment application.
Why this decision matters for bodies corporate and managers
- Developers are often dissolved, disinterested or hard to locate. This decision removes the obstacle of including them in building defect cases if they are not required.
- Bodies corporate have long brought defect claims as the plaintiff in their own name, and this decision confirms that they are legally entitled to do so.
- This decision reduces cost, delay and procedural complexity for bodies corporate pursuing defect claims.
Body corporate managers frequently support committees with building defect claims. This decision provides clarity by confirming that a body corporate does have the legal right (“standing”) to bring such claims in its own name, reducing the risk of disputes about whether the committee is entitled to take action.
Summary
The Westmark Milton decision confirms that a body corporate can take a builder to court directly in its own name for defects affecting common property, even if the body corporate wasn’t part of the original construction contract and even if the developer has since disappeared. By concluding that the concept of subrogation and the phrase “subrogated to” is used in the context of section 36(3) of the BCCM Act as transferring the rights of the original owner to the body corporate, the Court has removed a major source of uncertainty. Bodies corporate, committees and managers can now pursue defect claims with greater confidence, fewer procedural hurdles and without the cost or delay of involving a developer who has no ongoing role.
Written by Peter Waller, Special Counsel, Grace Lawyers, QLD
If you’ve discovered defects in your building and need guidance on bringing a claim, our QLD team can help. Call us on 1300 144 436 for clear, practical legal advice.
When Developer Control Derails a Defect Claim: The Road to Compulsory Management
NSW
Strata schemes can run into serious trouble when voting power and legal conflicts collide. This article explores allegations that a developer‑controlled majority disrupted a building‑defect claim, overturned key resolutions and ultimately left an Owners Corporation (OC) unable to act in its own interests. Through NCAT’s findings, strata managers can see how governance failures, ignored legal advice and entrenched conflicts of interest can push a scheme into dysfunction—and why compulsory management becomes the only workable circuit‑breaker.
Background
Birns & Ors v Querin & Ors (NCAT, 2025) is a textbook example of what can go wrong when developers keep a voting majority in a strata scheme—especially during a major building‑defect dispute.
The OC commenced building‑defect proceedings against the developer in 2023. An expert report estimated the cost of fixing the defects at $2.846 million. The developers’ expert, however, denied “37 of the 42 defects… amount[ing] to a denial of about 99% of the estimated cost of rectification.”
In an OC comprising 16 lots, the developer held nine lots and sold one lot to a related entity which in effect gave the developer an ‘effective majority’ control over 51% of the unit entitlement vote. Of the seven remaining lot owners, six separate lot owners collectively voted to commence and continue the defect case against the developer.
That imbalance of voting power became the centre of the conflict.
Up until about March 2025, the developer was excluded from any vote relating to the defect case pursuant to Part 3, Clause 11 of Schedule 1 of the Strata Schemes Management Act 2015 (the Act). However, this position changed and the developer was subsequently permitted to vote on resolutions pertaining to the defect case.
At a general meeting held in April 2025, the developers used their majority to:
- Void the earlier resolutions of the OC that resolved to fund the OC’s legal team and experts and advance the defect case ;
- Vote down attempts to reinstate those resolutions; and
- Pass new motions forcing the OC’s experts into conclaves with the developers’ experts, agreeing to the developers’ preferred timetable, and stopping all further legal steps until joint reports were produced.
Of the remaining seven lot holders, one lot owner voted with the developer while six others voted against the developer.
The Owners Corporation was Left Powerless
The OC’s lawyers provided strong legal advice about the adverse consequences of the developers’ actions at the general meeting. This included the OC’s legal representation and expert witnesses being defunded and the OC unable to even take the appropriate steps to comply with the resolutions of the developer to engage in conclaves and produce joint reports.
The OC’s lawyers warned that the developers’ voting power allowed them to in effect “negotiate with themselves” as both the controlling owners and the defendants in the defect case.
The NCAT matter
The six lot owners who voted against the developer at the general meeting commenced proceedings as applicants in the NCAT seeking orders for the appointment of a compulsory strata manager arguing that the OC had become dysfunctional. The combination of:
- developer control;
- cancelled legal funding;
- forced changes to litigation strategy; and
- the inability of the OC to act in its own interests
…created a situation where the OC could no longer operate and function properly.
The Applicant’s Case
The applicants argued the OC had become dysfunctional because the developers were using their voting majority to control decisions about the defect case even though they were the defendants in that case. This created what they described as a clear conflict of interest and effectively allowed the developers to “enter into settlement discussions with themselves”.
The applicants’ position was that the developers’ votes cut off funding for the OC’s lawyers and experts, leaving the OC unable to comply with Court orders, progress the proceedings or even act on the very steps the developers resolved at the general meeting, such as holding conclaves and preparing joint expert reports. The OC was “unable to even take the appropriate steps to comply with the resolutions of the developer.”
The applicants also pointed out that the developers passed a motion stopping the OC from taking any further steps in the Supreme Court proceedings until joint reports were completed—a hurdle that was impossible to clear without funding. Further, they argued that this behaviour was not in the best interests of all owners, contrary to section 9 of the Act, and clearly demonstrated dysfunction.
The Owners Corporation’s Case
The OC, the First Respondent in the NCAT matter (being represented by different lawyers to those in the defect case and who in effect were given instructions to defend the NCAT proceedings by the developer) argued that there was no dysfunction and therefore no need for a compulsory strata manager. They said that the developers were legally entitled to vote on all motions about the Supreme Court defect case, and the resolutions resolved by the developer at the general meeting were proper and allowed under the Act.
They also argued that concerns about the developers “self‑settling” was speculation. In their view, nothing the developers had done showed that the OC was failing to function.
The Developers’ Case
The developers raised a similar argument to that made by the OC.
They maintained that their voting decisions were rational and cost‑focused, not an attempt to “self‑settle,” and that they simply lacked enough information to approve funding for lawyers and experts. They also stated that the developers were willing to work with the OC and aimed only to “reduce unnecessary costs,” suggesting alternatives existed and a compulsory appointment was not justified.
Should a Compulsory Strata Manager be Appointed?
The Tribunal found that the conflict of interest created by the developers’ voting majority would continue throughout the Supreme Court defect proceedings, with no sign that their control will change. The developers had acted against strong legal advice, and offered no reasonable explanation for doing so, even though that advice warned that their voting decisions would “severely prejudic[e] the OC’s case.”
Because the dysfunction had already caused real harm—and was likely to continue—the Tribunal decided that appointing a compulsory strata manager was necessary to protect the OC and prevent further prejudice in the Supreme Court case.
The Tribunal ordered the appointment for 18 months, giving the defect proceedings time to run without interference from the conflict.
Summary
In Birns & Ors v Querin & Ors (NCAT, 2025), the Tribunal examined how a developer‑controlled voting majority disrupted an owners corporation’s ability to run a major $2.846 million building‑defect claim. The developers overturned key resolutions, blocked legal funding and acted against strong legal advice, creating ongoing conflict and dysfunction. To protect the owners corporation and prevent further prejudice in the Supreme Court proceedings, the NCAT made orders appointing a compulsory appointed strata manager to manage the OC.
Written by Daniel Radman, Managing Partner, and John Lim, Associate, Grace Lawyers
If your strata scheme is facing similar developer‑driven obstacles to pursuing building‑defect claims, contact our NSW Building and Construction team on 1300 144 436.
Why Owners Corporations Should Engage a Specialist Building and Construction Lawyer
NSW
Building and construction issues within strata schemes can be disruptive, costly and legally complex. Whether the matter involves building defects, incomplete works, contract disputes, or common property damage, lot owners face a legal landscape shaped by technical legislation, strict timeframes and specialised dispute‑resolution pathways. In this environment, the quality of legal advice is critical.
While many people instinctively turn to a local family or general practice lawyer, construction law is not an area where generalists can safely “dabble.” The risks are too high, and the consequences of incorrect advice can be significant. Engaging a specialist building and construction lawyer ensures that lot owners receive accurate, strategic and industry‑informed guidance from the outset.
This article explains why specialist expertise matters, outlines the key legislation governing building disputes, and highlights the essential points lot owners must understand when navigating construction issues.
The legislative framework governing building and strata disputes
Strata and construction matters in New South Wales are governed by a complex network of legislation, including:
- Home Building Act 1989 (NSW) – Statutory warranties, licensing, and residential building work requirements.
- Strata Schemes Management Act 2015 (NSW) – Responsibilities for common property, defect claims, and strata committee obligations.
- Building and Construction Industry Security of Payment Act 1999 (NSW) – Payment claims and adjudication processes.
- Civil and Administrative Tribunal Act 2013 (NSW) – NCAT’s jurisdiction and procedures.
- Design and Building Practitioners Act 2020 (NSW) – Duty of care obligations and compliance declarations.
- Environmental Planning and Assessment Act 1979 (NSW) – Development approvals and compliance.
A specialist construction lawyer works with these laws daily and understands how they interact in practice. A generalist lawyer may not have the depth of experience required to navigate this framework effectively.
Why lot owners need a specialist building and construction lawyer
Accurate interpretation of construction contracts
Construction contracts—whether for remedial works, upgrades, or new builds—contain detailed provisions relating to variations, delays, defects, payment schedules, and dispute‑resolution mechanisms. A specialist lawyer understands these clauses and ensures compliance with the Home Building Act and other legislation. This reduces the risk of disputes and protects lot owners from unfair contractual terms.
Understanding of technical construction issues
Building disputes often involve complex technical matters such as waterproofing failures, structural defects, fire safety non‑compliance, or incomplete works. A specialist lawyer is familiar with engineering reports, expert evidence, and industry standards. This allows them to quickly identify the core issues and develop a strategy grounded in both legal and technical realities.
General practice lawyers may struggle to interpret technical evidence or understand the practical implications of construction‑specific issues.
Effective dispute resolution that avoids costly court proceedings.
One of the most significant advantages of engaging a specialist construction lawyer is their ability to resolve disputes efficiently and without unnecessary escalation. Court proceedings can be lengthy, expensive, and disruptive for lot owners. A specialist understands the dispute‑resolution pathways available under the Home Building Act, the Strata Schemes Management Act, and the Security of Payment Act, and uses this knowledge to guide clients toward early, cost‑effective outcomes.
Through strategic negotiation, mediation, and targeted use of expert evidence, a specialist can often resolve issues long before litigation becomes necessary. This approach saves lot owners substantial time, stress, and financial burden.
Experience with NCAT and specialist forums
Many building disputes involving strata schemes are heard in the NSW Civil and Administrative Tribunal (NCAT). NCAT has unique procedural rules, strict evidence requirements, and specific expectations regarding expert reports and Scott Schedules.
A specialist construction lawyer:
- Appears regularly before NCAT
- Understands how tribunal members approach building matters
- Prepares compliant evidence and submissions
- Ensures statutory warranty claims are properly framed
- Manages expert evidence in accordance with tribunal rules
This experience significantly improves the likelihood of a favourable outcome.
Cost‑effective advice through efficiency
Although a specialist may have a higher hourly rate, they typically resolve matters more efficiently because they already understand the issues, the legislation, and the dispute‑resolution pathways. This efficiency often results in lower overall legal costs and a more streamlined process.
Proactive risk management for lot owners
A specialist construction lawyer helps lot owners and strata committees:
- Identify risks before signing contracts
- Ensure compliance with statutory warranties
- Recognise early signs of builder non‑compliance
- Respond promptly to defective or incomplete work
- Preserve rights under the Home Building Act and the Design and Building Practitioners Act
Proactive advice can prevent disputes and protect the financial interests of the entire strata scheme.
Key points lot owners must understand about building and construction disputes
Statutory warranty timeframes are strict
Under the Home Building Act, lot owners must act within:
- 6 years for major defects
- 2 years for all other defects
Delaying action can result in the loss of legal rights.
Common property defects are the Owners Corporation’s responsibility
Lot owners should understand:
- The owners corporation must repair and maintain common property
- Defect claims often involve both individual lots and common property
- The strata committee must act promptly to avoid further damage or liability
Expert evidence is critical
NCAT and courts rely heavily on expert reports. A specialist lawyer ensures:
- The right expert is engaged
- Reports comply with tribunal rules
- Evidence is strategically presented
Poorly prepared expert evidence can undermine an otherwise strong claim.
Early intervention prevents escalation
The earlier a specialist lawyer becomes involved, the more options are available to resolve the matter efficiently. Early advice can prevent:
- Builder disputes from escalating
- Payment issues from becoming Security of Payment claims
- Defects from worsening
- Rights from expiring
Not all lawyers understand strata construction law
General practice lawyers may unintentionally:
- Misinterpret construction contracts
- Miss statutory deadlines
- File incorrect applications
- Provide incomplete or inaccurate advice
These errors can significantly weaken an owners corporation’s position.
How Grace Lawyers can help
Grace Lawyers has a dedicated team of Building and Construction specialist lawyers who act exclusively for owners corporations. Daniel Radman, Managing Partner at Grace Lawyers, leads the firm’s building and construction practice. Daniel and his team have acted for Owners Corporations in numerous leading building cases including the only two strata defect matters decided in the High Court of Australia:
- Pafburn Pty Ltd & Anor v The Owners – Strata Plan No 84674 [2024] HCA 49
- Brookfield Multiplex Ltd v. Owners Corporation Strata Plan 61288 & Anor [2014] HCA 36
Summary
Construction and strata disputes are complex, technical and governed by strict legislative requirements. Engaging a specialist building and construction lawyer ensures that lot owners receive accurate, strategic, and efficient advice tailored to the unique challenges of building defects, contract disputes, and common property issues.
From contract review and risk management to dispute resolution and NCAT representation, a specialist lawyer provides the expertise necessary to protect your rights and achieve a cost‑effective, timely resolution. Given the financial and legal risks involved, choosing a specialist is not only prudent—it is essential.
Written by Daniel Radman, Managing Partner, Grace Lawyers
If you require guidance on a strata, building defects, or construction dispute, our specialist lawyers are ready to assist. Contact us now on 1300 144 436 for precise, informed advice that safeguards your project and your position.
NSW Court of Appeal Confirms Builders Have No Automatic Right to Return and Rectify Defects
NSW
In the recent Court of Appeal decision of Ceerose Pty Ltd v The Owners – Strata Plan No.89074 [2025] NSWCA 235 the court upheld the long-established principal that the builder is not entitled to return to rectify their defects and confirmed that whether or not they should be allowed to return will always depend upon what is reasonable.
The case involved the “Eliza” building on Elizabeth Street in Sydney, overlooking Hyde Park and St Mary’s Cathedral which made headlines when completed in 2014 after the three-storey penthouse sold for a then record $15 million.
Does a builder have a right to return and rectify strata defects?
The Owners Corporation of SP 89074 served a 600-page expert report claiming more than 300 defects including urgent fire safety works, drainage, flooring and bathroom issues. The builder responded by agreeing to return to rectify nearly 100 of the defects and stating that they were always ready, willing and able to rectify any genuine defects.
This is common for a large builder because it is actually highly unlikely that there will not be any defects in a large building and it will always be much quicker and cheaper for a builder to rectify their own defects because they are familiar with their site and the products used. There is also always the danger that a new builder will charge more to rectify another builder’s defects and will often discover more problems.
This is partly why the NSW government, which is responsible for licensing builders, includes section 48MA in the Home Building Act such that:
“A court or tribunal determining a building claim involving an allegation of defective residential building work or specialist work by a party to the proceedings (the responsible party) is to have regard to the principle that rectification work by the responsible party is the preferred outcome”.
In NCAT, where the vast majority of these building claims are initially brought, the tribunal’s stated preferred position is for the original builder to return to rectify their own defects often by agreement or by an NCAT work order.
Can owners deny builder access to rectify defects?
There is however no actual “right” for the builder to return. After completion of the building it is owned by the Owners Corporation and they can determine who enters the site to do work. In the Eliza case, the owners decided they had lost faith in the ability or the willingness of the builder to return to adequately rectify the defects. This case was similar to other Supreme Court cases like SP 76674 v Di Blasio and Owners Strata Plan 89041v Galyan Pty Ltd. I previously had an NCAT case where the original builder still lived in the building and the other owners had all lost faith in his ability to rectify the building properly even though it was much cheaper than hiring a new builder.
Reasonable owners will generally allow the original builder back to rectify defects because it does not cost them anything and usually gets the building fixed. However if they keep having to beg the builder to return and everyone gets annoyed with each other and the defects still don’t seem to be getting fixed then the owners may have to commence legal proceedings because their statutory warranty rights are about to expire. At this point the goodwill of the builder can also expire.
What is an owner’s duty to mitigate loss in a building defect claim?
In the case of the Eliza building, there were two key issues that the Court had to determine. The first was the owners’ “duty to mitigate”. Where a Plaintiff is claiming loss against a Defendant they have to take reasonable steps to minimise their damage. That may include allowing the builder back to fix the defects if that was reasonable. Similarly the Plaintiff is not entitled to an upgrade. So if you buy a rundown old unit with chrome taps that don’t work, you can replace them but if you choose a solid gold fitting you cannot expect the original builder to cover the extra cost of the better product.
In the Eliza building after apparently a number of requests by the owners to the builder to rectify defects the owners advised the builder that they had lost confidence in the builder and that they were unwilling to let the builder have any further opportunities to repair the defects. The case was referred to a Supreme Court Referee who produced a report on liability issues as well as a report on the quantum of the cost to rectify the defects. The builder argues that the owners had failed to mitigate their loss because they had refused to allow the builder access to rectify the defects at no cost to the owners. The Referee concluded that the onus was on the builder to prove that the owner’s decision to deny access to them was unreasonable in all the circumstances. He concluded that the owners had not acted unreasonably in refusing access to the builder to carry out rectification.
The Supreme Court judge accepted the Referee’s report and entered judgment for the owners in the sum of $1.95 million. The builder appealed arguing that the judge made an error regarding the owner’s duty to mitigate their loss and also that there was a “positive obligation” on the owners to provide the builder with an opportunity to rectify the defects.
Who must prove that refusing access was unreasonable?
The key issue before the Court of Appeal was which party had to prove that the owners’ refusal to allow the builder to return was unreasonable. The builder argued that once they had raised the issue in their defence of the failure to mitigate then the onus of proof shifted to the owners to prove that their refusal to allow the builder to return was unreasonable. The Court of Appeal ultimately agreed with the owners and the court that the builder had the duty to prove that the owners had been unreasonable and that they had failed to establish that.
Why did the Court of Appeal rule in favour of the owners?
The builder had argued that the owners may have manufactured the argument of their loss of confidence in the builder because they preferred to get a lump sum award that they could use when and how they chose. The Court of Appeal referred to the previous cases and determined that there is not any special common law rule applicable to building contracts in this regard and that the owners were not required to demonstrate excessive diligence nor perfection.
As is so often the case it came down to what the court determined to be reasonable in all the circumstances and ultimately the builders failed to establish that the owners had been unreasonable.
What are the practical lessons for owners corporations and builders?
Key takeaways:
- There is no positive obligation on the owners to provide the builder with an opportunity to return to rectify their own defects;
- A refusal to allow the builder to return to rectify can be argued as a failure to mitigate the owners’ loss, but that is just the start of the argument. The builder has the onus to prove that the owner’s refusal of access was unreasonable;
- The onus did not shift to the owners to prove they were not unreasonable, the onus was always on the builder to prove that the owners were unreasonable;
- The Court of Appeal in analysing the evidence of the owner’s behaviour reiterated that in the case of a nil all draw in terms of evidence the party with the onus of proof (here the builder) had failed to prove the refusal was unreasonable and therefore they lost;
- It will be more difficult to prove that an Owners Corporation is being unreasonable because it is a collection of minds that has an obligation to do what is best for the whole Owners Corporation; and
- In most cases it will still be cheaper, quicker and easier to allow the original builder to return to rectify the defects.
Summary
In Ceerose Pty Ltd v The Owners – Strata Plan No. 89074 [2025] NSWCA 235, the NSW Court of Appeal confirmed that owners are not obliged to allow a builder to return and rectify defects. While rectification by the original builder remains the preferred outcome, owners may refuse access if that is reasonable in the circumstances. Importantly, the builder bears the burden of proving the refusal was unreasonable. The decision reinforces that each case depends on its facts and the standard of reasonableness.
If you require guidance on building defect claims, statutory warranty disputes, Owners Corporation rights, or construction litigation, please contact our Building and Construction team on 1300 144 436.
Written by Duncan Campbell, Building and Construction Partner, Grace Lawyers
Last updated on 23 July 2026
Supreme Court Clarifies Major Waterproofing Defects and the Duty under the DBPA
NSW
For strata managers dealing with persistent building defects, limitation periods and uncertain liability, the Supreme Court’s decision in Strata Plan 92183 v Samdora Pty Ltd [2026] NSWSC 406 is a significant development. The judgment provides valuable guidance on when waterproofing and drainage issues may be classified as “Major Defects” under the Home Building Act (HBA), while also reinforcing the obligations of builders and nominated supervisors under the Design and Building Practitioners Act 2020 (NSW) (DBPA). The case offers important lessons for managing defect claims, assessing risk and protecting the interests of owners corporations.
Were the waterproofing defects considered major defects?
The case concerned the development of a nine-unit residential building in Mangerton by the Defendants. The case started as many do in NCAT and there was a long history of emails between the parties trying to come to an agreement about what defects the builder agreed to return to rectify. Unfortunately, before the builder managed to complete the rectification work adequately, it fell into administration. The Supreme Court then had to review many “without prejudice” emails to determine what had exactly been “agreed” to and by which parties.
The original agreement for the rectification work dated back to 2019 and, after the disappearance of the builder, the case proceeded in the Supreme Court against the Developer as well as the nominated supervisor of the builder in his personal capacity under the DBPA.
In respect of the HBA claim, it had been agreed between the parties that, due to the age of the building, only claims relating to major defects remained claimable by the Plaintiff (owners corporation). The remaining defects claimed were categorised as “general” and “waterproofing”. The court heard arguments between the parties as to whether these defects, in particular the “waterproofing” defects, were Major Defects.
The definition of what is a “Major Defect” under the HBA is in section 18E which refers to:
“a defect in a major element of a building that is attributable to defective design, defective or faulty workmanship, defective materials, or a failure to comply with the structural performance requirements of the National Construction Code…”
So, what is meant by a “Major Element”?
A “Major Element” is defined by section 18E of the HBA as:
“…an internal or external load-bearing component of a building that is essential to the stability of the building, or any part of it (including but not limited to foundations and footings, floors, walls, roofs, columns and beams), or a fire safety system, or waterproofing…” and that “… causes, or is likely to cause… the inability to inhabit or use the building (or any part of the building) for its intended purpose, or the destruction of the building or any part of the building, or a threat of collapse of the building or any part of the building”.
The owners corporation’s expert argued that all the hydraulic defects were “waterproofing” and therefore were Major Defects. On behalf of the Defendants, the Court was referred to the NCAT Appeal Panel decision of Ashton v Stevenson [2020] where the Panel, had regard to the fact that the design and purpose of the drainage and bund in an outdoor terrace area was to collect and control rainwater in considering whether it was “waterproofing”. It was submitted by the Defendants that, based upon the Ashton decision, only if both the design and purpose of a defective building element was to prevent water from entering the building, only then could it meet the description of “waterproofing” for the purpose of the HBA. The Court decided that the Panel was not intending to establish a “design and purpose” test rather it was merely undertaking the task of making a factual finding as to whether a particular element is “waterproofing”. Kunc J decided that:
“… an element will be waterproofing if its purpose is to prevent ingress of water into a building. This means that in some cases a particular element may be waterproofing because of how it is deployed and in other cases it will not be waterproofing.”
In this regard, the Court found that the stormwater overland flow path was a Major Defect, as was the rainwater overflow and balcony drainage system. The Court did not accept that actual evidence of water ingress was required.
Negligence under the DBPA: What must be proven?
With respect to the claim against the nominated supervisor of the builder, the Court also gave some clarification as to what needs to be established for a claim in negligence under the DBPA. The judge referred to the general principles of negligence under the Civil Liability Act 2022 (NSW) including that a person is not negligent in failing to take precautions against a risk of harm unless the risk was foreseeable and not insignificant and that in the circumstances a reasonable person in that position would have taken those precautions.
Kunc J referred to the leading High Court decision of Pafburn Pty Ltd v Strata Plan 84674 confirming that the duty was a personal non-delegable duty on the supervisor Mr Nassif and therefore he could not discharge the duty merely by exercising reasonable care in arranging for another person to carry out any work or task within the scope of the duty.
Can a nominated supervisor be personally liable under the DBPA?
The Court went on to find that Mr Nassif had breached his duty under s 37 of the DBPA because he had failed to exercise reasonable care to ensure that the work was relevantly compliant with the statutory warranties in s 18B(1)(c) of the HBA warranting that the work would comply with the warranties or any other law. So, the precaution that he had failed to take against the risk of harm to ensure the work was relevantly compliant was to have properly carried out “an active supervisory role” during the construction process by regular inspections and checking of the work such that the defects would have been identified and rectified prior to the completion of the development. The negligent failure to play an active supervisory role was a necessary condition of the harm because, if he had undertaken that role properly, the harm of the defects and the cost of repairing them would not have arisen because the defects would not be there.
What does active supervision require under the DBPA?
Those acting for Mr Nassif tried to argue that he relied on the fact that other professionals such as the certifier had inspected the building work but did not identify any of the defects however that argument was rejected by the Court and in particular noting that “it is, regrettably, a common experience that buildings for which an occupation certificate had been issued are later found to have defects.” In the same way, it is also regrettably a common argument that because a building has an occupation certificate then it must be free from defects. Unfortunately as we are aware in most cases that is not the reality.
What are the key takeaways for strata managers?
- What is or is not a major defect will be a factual finding for the Court or NCAT member to make in any particular case and some particular element may be waterproofing in some cases whereas the exact same thing may not be seen as waterproofing in another case;
- A builder can be in breach of its duty under section 37 of the DBPA by failing to reasonably exercise an active supervisory role to ensure that the building complied with the statutory warranties.
Summary
Strata Plan 92183 v Samdora Pty Ltd [2026] NSWSC 406 clarifies when waterproofing and drainage defects may constitute Major Defects under the Home Building Act and confirms that nominated supervisors can be personally liable under the Design and Building Practitioners Act for failing to actively supervise construction works. For strata managers, the decision provides practical guidance on identifying viable defect claims, assessing limitation risks and pursuing recovery against the parties responsible for defective building work.
If you would like advice on identifying viable building defect claims and pursuing recovery from developers or other responsible parties, contact Grace Lawyers on 1300 144 436 or enquiries@gracelawyers.com.au
Written by Duncan Campbell, Partner and Paul Berrill Special Counsel, Grace Lawyers Building and Construction.
Last updated on 14 August 2026
Victorian Supreme Court Redefines Balcony Repair Responsibility in Damjanovski Decision
VIC
This article summarises the recent Supreme Court of Victoria decision in Damjanovski v Owners Corporation 1 Plan No. PS503570D [2026] VSC 656.
The decision is one of the most significant Victorian decisions in recent years and has far-reaching consequences for Owners Corporations, strata managers and lot owners.
The briefing will examine the factual background to the dispute, the Supreme Court’s interpretation of the relevant plan of subdivision, the Court’s consideration of the meaning of “interior face”, and the implications of the decision for determining whether balcony waterproofing systems form part of common property or private lot property.
How did the balcony repair dispute arise?
The proceeding concerned a long-running dispute regarding water ingress originating from a fifth-floor balcony within a residential apartment development in Maribyrnong.
Mr Damjanovski purchased the apartment off the plan in 2002. From approximately 2007 water ingress was reported in apartments beneath Mr Damjanovski’s apartment. Expert investigations ultimately determined that water was entering lower lots due to several defects, including but not limited to:
- the tiled balcony surface;
- the waterproofing membrane; and
- the screed beneath the tiles.
The Owners Corporation contended that the balcony floor, including the tiles, waterproof membrane and screed, formed part of Mr Damjanovski’s lot and that he was therefore responsible for repairing and maintaining those components.
Accordingly, Notices to Repair were issued in November 2022 and March 2023 requiring Mr Damjanovski to undertake remediation works to the balcony.
Mr Damjanovski commenced proceedings in VCAT seeking declarations that the Notices to Repair were invalid and that responsibility for the defects rested with the Owners Corporation.
At first instance, VCAT accepted the Owners Corporations’ position and concluded that the boundary of the lot was located at the surface of the structural concrete slab. On that basis, VCAT determined that the tiles, screed and waterproof membrane situated above the slab formed part of Mr Damjanovski’s lot.
Mr Damjanovski appealed the decision to the Supreme Court of Victoria.
What laws govern balcony repair responsibility?
The principal legislative provisions considered by the Supreme Court were:
- sections 4, 46 and 47 of the OCA;
- sections 48 and 49 of the OCA;
- section 129 of the OCA;
- section 12 of the Subdivision Act 1988 (Vic) (SA);
- the relevant plan of subdivision; and
- the Subdivision (Procedures) Regulations 2000.
The dispute ultimately centred on the proper interpretation of the plan of subdivision and, the meaning of the notation that boundaries defined by buildings were located at the “interior face” of the building.
What was the Supreme Court decision?
Ultimately, the Supreme Court overturned VCAT’s interpretation of the plan of subdivision. Specifically, the central issue was whether the expression “interior face” referred to:
- the surface of the structural concrete slab; or
- the visible surface of the completed balcony floor.
VCAT adopted the former approach, finding that the structural slab represented the relevant boundary and that everything above it formed part of the lot. Harris J rejected that interpretation.
Her Honour observed that the relevant question was where the boundary lies when a balcony floor consists of multiple building layers, including:
- a structural concrete slab;
- screed;
- waterproof membrane; and
The Court held that “interior face” referred to the interior face of the building itself, being the visible face of the completed building rather than the structural slab lying beneath the finished surface. Harris J stated:
“the better view is that the effect of the Plan of Subdivision is that the concrete slab floor of the Balcony, and the slab, membrane and tiles affixed to it, is common property.”
The Court further held that “the surface of the tiles is the interior face” and concluded that the tiles, waterproof membrane and screed should all be considered common property.
Accordingly, the Court held that:
- the tiles were common property;
- the waterproof membrane was common property; and
- the screed was common property.
Because those building elements were determined to be common property, the Court determined that VCAT had erred in declaring that Mr Damjanovski breached section 129 of the OCA by failing to repair and maintain his lot.
The Court further held that the Notices to Repair could not properly be supported by section 48 of the OCA because that section only applies where repairs are required for a lot owner’s lot.
Why is the Damjanovski decision so important?
This decision is likely to become the leading Victorian authority on the interpretation of interior faces in plans of subdivision prior to 2011.
Perhaps most significantly, the decision substantially undermines the approach previously adopted in Owners Corporation PS508732B v Fisher [2014] VCAT 1358.
In Fisher, VCAT held:
“the interior face of the building means, the interior face of the structure of the building rather than the top surface of whatever is fixed to the structure of the building.”
In Fisher, tiles and waterproofing located above a structural slab were generally treated as lot property.
Harris J expressly rejected that approach.
Her Honour held that:
- “interior face” refers to the interior face of the building, not the structural slab;
- the visible completed surface is the relevant reference point;
- the reasoning in Fisher incorrectly focused on the structural slab rather than the completed building surface; and
- section 132 of the OCA does not support the proposition that everything attached above a structural slab automatically forms part of a lot.
Notwithstanding the above, the Court also reinforced the relevance of the benefit principle. Although the balcony floor components were found to be common property, the Court noted that repair expenditure may nevertheless be recoverable from a benefiting owner pursuant to sections 24 and 49 of the OCA.
Which owners corporations are affected?
Notwithstanding the above, the decision is likely to have limited application to plans of subdivision registered after 2011. A significant feature of the dispute was that the relevant plan used “interior face” without being properly defined.
Since 2011, certainty has been provided by the Subdivision (Registrar’s Requirements) Regulations 2011 and, subsequently, the Subdivision (Registrar’s Requirements) Regulations 2021. Regulation 10(4)(a) now expressly provides that an “Interior Face”:
“lies along the interior face of any wall, floor (upper surface of elevated floor if any), ceiling (underside of suspended ceiling if any), window, door or balustrade of the relevant part of the building and any internal coverings, waterproof membranes and fixtures attached to walls, floors, and ceilings are included within the relevant parcel“.
Accordingly, while Damjanovski is now the leading authority concerning the interpretation of pre-2011 plans containing “interior face” notations, its broader application to plans governed by the 2011 and 2021 Regulations is limited.
What does Damjanovski mean for future balcony repair disputes?
There is now inconsistent interpretation of “interior face” notations in plans registered before and after 2011, which leads to uncertainty regarding the ownership of building elements and responsibility for their repair and maintenance, which should be consistent.
The practical significance of Damjanovski is that it challenges a number of assumptions regarding the ownership and maintenance of balcony floor systems in Victorian Owners Corporations.
For plans of subdivision registered prior to 2011 which utilise “interior face” notations, the decision provides strong authority that balcony floor systems, including tiles, waterproof membranes and screed, may constitute common property rather than lot property.
Importantly, Owners Corporations and managers should not assume that responsibility for balcony waterproofing rests with the lot owner simply because the balcony is attached to, or exclusively used by, that lot. Rather, the starting point must always be a careful examination of the relevant plan of subdivision to determine the location of the boundary between lot property and common property.
Despite the Court’s finding that the balcony floor components were common property, Damjanovski also confirms the continuing importance of the benefit principle. Owners Corporations should remember that ownership of an asset and liability for the cost of repairing that asset are separate questions. Even where works relate to common property, sections 24 and 49 of the OCA may permit costs to be allocated to a particular lot owner where the works are undertaken wholly or substantially for the benefit of that lot.
Accordingly, the decision is unlikely to eliminate disputes concerning balcony repairs. Rather, future disputes are likely to focus on two separate issues:
- whether the relevant building element forms part of common property or the lot; and
- if the element is common property, whether the cost of repair should be borne wholly or predominantly by a benefiting lot owner under the benefit principle.
Subject to any appeal, Owners Corporations and managers should carefully consider the implications of Damjanovski when determining responsibility for balcony repairs and associated costs and to seek legal advice for plans of subdivision registered prior to 2011.
If you require guidance on the impact of Damjanovski or responsibility for balcony repairs under your plan of subdivision, please contact the Victorian Grace Lawyers strata team at enquiries@gracelawyers.com.au or 1300 144 436.
Written by Leila Idris, Partner, and Christopher Oster, Special Counsel, Grace Lawyers
Last updated on 26 October 2026